Desalination, 30(1979)1S+21 QELwvier9ckMicpUb~ Company, Amstefilam-I%ntedinTheNethe&mds
TRE YUMA DESALTING PLANT MANUELLOPEZ U.S. Bureau of Reclamation
(Retired)
ABSTRACT
The 96 million
gallon
per
day
desalting plant is part of a complex pro-
Yuma
ject intended to solve = long-standing water quality problem between the United States and Mexico, irriqation tain
return
a 115 mg/l
Designed to treat flows,
the
plaut
differential
up to
will
betwaen
129,000
deliver
water
acre-feet
283 cg/l
of
3200
product
mg/l
water
to main-
to U. S. users and to
delivered
Mexico. Design
of
the
pretreatnent and
plant
requirements,
instrumentation
lime
softening
Nine
menbrane
Two
spiral
physical
1979
of
with
by au extensive
membraue
perfo-ce, Tut
performance.
systems
(both
reverse
economic
the
pretreatment
for a-d
osmosis
and of
Sumner
osmosis
systems and
the main of
and
were
and
were
chosen
for
as most site
installation
equipment
tested. the
Partial
final
were
from
and
for award of desalting
design.
tested.
efficient
preparation
is scheduled
to detellnine
aud
electrodialysis)
for
basin
plant
was
Program
capacity
systems
chosen
contracts
sedimentation
research
plant
filtration
reverse
viewpoint,
intakes
construction
scheduled
preceded
followedbymulti-media
muud
and
ruction
was
const-
summer equipment
1980_
Based on January 1979 prices, total cost of the desalting conplex is approximately $190 million cost
per
daily
of desalted
gallon
water
(including interest of
(capital
installed
during
capacity
amortization
plus
construction).
is approximately operation
and
The
investment
$2_ per maintenance)
1000
gallons
is $C3.77.
INTRcWCZTION The
1944
United
States-Mexico treaty for the utilization of water of the 15
LOPEZ
16 Colorado annual most
Tijuana
quantity streams
iorate was of
and
of
that
as the
about
are
used
800 mg/l
the Wellton-Mohawk availability
1500
District
of excess Mexico
formally
measures
to improve
the
mesaures
were
undertook The
not
to find
culmination
Water
Commission.
which
for
imately
the
of Norelos million at
totally
Purposes
Dam
(ppm)
of
242
over
of
annual
and
the
which
Like
quality
deter-
quality
of the
increased
from
the
an annual
saline
began
and 242
several
treaty
water
salinity
average
drainage
at the
same
average
and
the
just of
of
from
time
point
for
United
that
the
to this
problem".
most
of Colorado
Boundary
and
significant that
annually
of no more
These in 1972
it provided
irrigators
interim
States
International
delivered
salinity
of
to Mexico.
soiution
the
is that
salinity
a series
available
provisions,
water
average
followed
made
to Mexico
Minute
Dam (the last diversion
Imperial
water
discussion
an annual
the
the
was had
1961,
River
there
definitive
this
acre-feet have
and
acceptable
effort
quantity
River-
to an end.
of
a "permanent,
both
a guaranteed
Colorado
of highly
Colorado
protested
Minute
1,360,OOO
came
quality
of that
the
the
to Mexico
discharge
to Mexico
from
occurred
available
into
allots
Until
events
mq/l:
waters
again,
stream.
two
made
Grande
of water
over
down
waters
Rio
feet
and
Then
to nearly
the
acre
progresses
River
of
over
to Mexico_
Colorado
In 1961
and
l.!iOO.OOQ
river
acceptable the
Rivers
the
of
approx-
to Mexico
upstream
than
115230
River
water
arriving
United
States).
in the
parts
per
IEIPLE~~ENTFJ.TION Several
of the
construction
of works
United
States_
93-320
(PL93-320),
1974.
24,
ing plant of the
the
The
Slough most
or other
the
the
Project, stream
in Mexico, important
for
River
the and factor
Basin
the
plant, plant
necessary
affecting
Salinity
the
water
other
of
funds
by
the
Control
enacted
COLUPleX,
from
of
on
in Public
Act,
including
the Wellton-Mohawk of a bypass drainage
appurtenant size
implementation
is contained
extension and
for
expenditwes
of desalting
of drain
desalting
dependent
expenditures
construction
salinity
are
requiring
these
a pre-treatment
from
242
measures
Colorado
authorizes
to reduce
Gila
of Minute
Authorization
which
reject
Clara
provisions
June a desaltdivision
drain
waters
Law
to carry
to the
Santa
works. the
desalting
plant
(therefore
17
LOPEZ
it's
cost)
is the
also
authorizes
acquisition
that
implementing
the
area
by
Colorado
desalting
PL93-320
River.
plant
STUDIES
would
to the
a series
data_
studies
These
ing,
optimization
more
important 1.
it was be
flows
through
division,
return
preliminary
flows.
fran
75,000
improvement
acres
program
and studies
to 65,000
acres
in cooperation
with
Using
projecting
future
estimated
that
70% recovery for the desalting
the
salinities
of
a 100 million
the
gallon
drain per
water
day
and
(mgd)
required.
studies
Desalting
of
the
were
process
available
studies
desalting
plant
and
undertaken
to provide
selection,
o_perating
equipment,
and
definitive
the need desQn
for
and
procurement
experience,
size
high
field
test-
requirements.
The
were:
process
selection.
distillation,
of advance
reduced
of
size
included
of
including
use
All
major
crystallization,
technology
commercially
desalting
and
processes
ionic.
available,
Since
the
list
were
PL93-320
considrequired
of process
were
to: Distillation-multi-effect.
a) and
vapor
multi-stage
flash,
vertical
tube
evapor-
compression. Ionic-ion
b) though
return
therefore
Wellton-Mohawk
division
efficiency
and
unprecedented
reliability,
ation
of the
of the
PL93-320
irrigation
to minimize
size
treated.
UNDERTAKBN
Due
the
size
of
175,000 acre-feet per year.
plant required
ered,
the
an irrigation
to be
farmers could reduce the drainage from 220,000 acre-feet per ye&r to
approximately
the
the
water
quantities
improvements
reducing
and
of the
to reduce
efficiency
indicated
of drainage
reduction
of lands
irrigation
of
amount
economic
and
exchange,
physical
electrodialysis
evaluation,
and
reverse
electrodialysis
and
osmosis. reverse
Based osmosis
on were
selected_
Membrane Plant
2. ing plants, design. designers ing
ranging
operation
in size and
in avoiding
criteria_
Operating from
Experience. 2,500
maintenance_ problems
and
The
gal/d
Eleven to 2.0
purpose
selecting
Mgal/d
of the
proper
commercial were
analysis
material,
membrane analyzed was
desaltregarding
to assist
equipment
and
the operat-
LOPEZ
18
meet
sizing
Plant
3.
unpredictable
Wellton-Mohawk
drainage
the desaltinq
ditions
and was
feet.
levels
undertaken
It was
treat
167,000
ditionssome
four
of
the
85%
15% of
would
the
have
time
the
quality of
the
drainage
entire
based
on
been
systems
would
replaced
with
By
the
waters
construc-
time
this acre
be adequate
to
hydrloqic
con-
at capacity from
con-
to 167,000
future
operate
and
hydrologic
would
the postulated
to
River
was
reduced
which
life
Colorado
flows.
plant
plant
its
of possible
had
a 96 mgd
and
of both
drainage
desalting
to be bypassed
throughout
13 sequences
for
probable
the
time,
and
model
to procure
of
required
Wellton-Mohawk
estimated
acre-feet
be
quantity
operated
annual
decided
will
A complete
was
therefore
About
drainage
in the
flows. plant
plant
The
variations
ted and
study
study_
the
and
Colorado
River.
4.
Field
wst
Facility
ment
suppliers
Testing-Extensive
since
1974
to provide
with
data
on desalting
Wellton-Mohawk system bids
drainage
parameters.
by the
Several
tested. field
and
pre-treatment
of
testing
and
requirements addition,
more the
membrance
test
been
Bureau
and
faciliate
evaluation
flocculation
were
it could
reliably
less
expensively
testing desalting
2900 was
Roga
2.
Envirogenics
3.
Dupont
4.
Dow
conducted at
test
Universal
Oil
fine
fine
for over the
(spiral
(hollow
(hollow
of
reduced
meet
by
the
earth,
were
threemonths
the pre-treatment
water
the pezmanganate of the
in better
government.
cold-lime
cold-lime
salinity
pre-treatment result
diatomaceous partial
eguip-
on pre-treated
would
Within
than the
desalting
optimize
bids
Desalting
potassium
were
screen
chosen the
for lime
quality
process.
feedwater
from
mq/l.
equipment
Division
1.
process
and
-partial
constructed.
Yuma
operating
of the
and
and
and
developed
filtration.
permanganate
trains
softening
systems
infornntion
that
lime
equipment
the
including
at the
Reclamation
pre-treatment
alum
and
undertaken
of
demonstrated
to approximately
Membrane
would
have
modules
that
potassium
small
process
felt
zeolite,
these,
the
to test
systems,
manganese
Two
softening
mq/l
and
It was
suppliers
permanganate,
tests
wound fiber
fiber
R 0) R 0)
R 0)
four
years.
facility; Products
they
Wine
manufacturers
were:
(spiral
wound
R 0)
tested
In 3200
LOPEZ
The
19
Asahi (sheet
5,
DOW
6.
Ionics
7_
Westinghouse
8.
Aqua
9.
Iiydranautics
(spiral
demonstrated
successful
tests
trodialysis
Chem
units
ing
rejuvenation
E D)
(tubular
R 0)
(sheet
flow
E D) wound
drainage
in May
levels,
design
1978
criteria
after
operation water
and
recovery
elimination
solutions,
and
R 0)
long-term
hexmetaphosphate
units
terminated
path
on pre-treated
sodium
desalting
E D)
(tortuous
minimum and
flow
of
of
provided
rates,
selection
data
and
elec-
on maximum of
materials
All
was
osmosis
evaluation
inadequate
for procurement.
equipment
reverse
testing
and
chemical
formerly on
these
cleanused
units
on were
made.
PROCUREMEXP In the ment The
for
spring the
of
Yuma
1976
the
Desalting
FlPP expressed
the
Request Plant,
desire
for
Proposal
Solicitation
of the
(RFP) No,
Government
for Membrane
DS-7186
to award
Desalting
Negotiated,
a contract
or
was
Equip-
issued.
contracts
which
. include city
at least
to one
capacity
l_ perform
at
75%
of
to state Plant
time 3.
rating
and
4_ to verify portion
20
the
RFP
of
for
rated
usable
was
in the
best
were
proposed
Test
performance
data
to award of
which during
to replace
within
24 hours
the membrane plant
the
entire
the
Government.
any
element
plant
capa-
Minimum
plant
storage contractor
submitted
with
which
does
Offerors
cleaning.
not
were
re-
elements_ was
described,
with
probable
desc-ribed.
Rating-for
included
of
operation
parameters
Performance
Unit-each
interest
required
for
in plant
Element
right
were:
Operation-anticipated
and
the
mgd.
lifetime
degradation
Proof
reserved
performance
variations
Train
curve
cleaning,
was
Warranties-Offerors
2. down
if it was
offeror,
features
but
process,
to be offered
Salient
quired
two
purposes
of equipment
allowances
for degradation
of
and
1 year,
is required his
proposal
for
to
and
removable
a safety
furnish shall
design,
a
by
factor.
a proof
test
unit
be a representative
of the plant5.
Evaluation
Criteria-a
list
of elements
(in descending
order
of
importance)
20
ID?EZ
for
evaluating
brane
each
proposal
characteristics,
was
included_
warranties,
(other
desalting
unit
maintenance,
operation,
6.
Cost
Evaluation-a
complete
was
described
economic
impact
items
be
to
of
by
Glass
4.
Fluid
5.
Hydranautics-spiral
6.
Ionics-tortuous
7.
Permutit/Dow-hollow
three
of Goleta,
proof
ing Test
element
properties
down,
with
time,
etc.
economic
evaluation
of
and
variable
components
as well
equipment, were
mem-
charac-
for
Proposals
the pro-
structures
received
as
and
the
other
from:
D
E
R 0 R 0 Universal
Oil
Products-spiral
wound
RO
R 0
fiber
R 0
of negotiation to award
Award
was
unsuccessful 22.4
Products
tests
Facility_
for
site
In the meantime,
units Final
Mgd
of San
and two
delayed
at
until
$7.2
evaluation,
contracts,
million;
California,
the
both
October, The
offerors.
Diego,
in the
schedule
calls
for award
intakes
and
installation with
and
and
plant
intake
to increase plan
of the
of desalting
received
of the the
project
sedimentation
initial
been
design
legislation
changes
the
have
preparation
several
later,
fine
for
membrane
design,
E D
intentions
of the
Oil
wonnd
process
final and
government
for
spiral
1978,
however,
award
was
to Fluid
for
73-3
wound
revof a
because
to Hydranautics
Systems
Mgd
announced
Division
at
$20.6
million.
at
the Yuma
STATUS
The
tions
its
of
path
California,
Universal
CURRENT
Division
membranes.
by
wound
shut
on perpheral
flow
fiber
15 months
1977,
fixed
part,
of membrane
and
procedure both
in
experience,
start-up
Government_
fine
Systems
and
were.
degradation
offered
(Japan)-sheet
Envirogenics-spiral
osmosis
included
the
3.
approximately
itself),
equipment
DuPont-hollow
protest
of
the
2,
in October, erse
which
furnished
I._ Asahi
After
membrane
testing
teristics
posals
than
These
operation
and the
for
in summer
equipment
are
desalting
is being
contracts
basin
and
plant
tested
is pro&ding
sedimentation appropriation considered site 1979_
is scheduled
in 1982,
being
by
and
Desalt-
solicita-
system
has
been
ceiling
and
to authorize
Congress.
preparation
and
Construction to begin
The
issued.
current
construction of the main
approximately
of plant
a year
COST
DATA
Plant
Data
Installed Product
capacity
95.7
water
90,570 or
Plant
2.95
acre-feet/v 10 gal/F
x 10
costs
Investment
costs
(January
1978
Annual
equivalent
investmen$
Annual
operating,
maintenance,
Total
Unit
Mgd
Cost
annual
Annual
investment
Annual
operating Total
costs costs
annual
(50 yrs.-5
replacements
equivalent
of Desalting
prices)
cost
cost
($190,000,000) S/89.) and
energy
11,430,000
11.580.000 $ 23,OlO.OOO
Water per per
1000 1000
equivalent
gallons gallons
cost
$ 0.38 0.39 s 0.77