~nnals Qf Nuelear E~ergy, Vol.5, pp.305 to 3 2 0 . Pergamon Press Ltd 1978. Printed in Great Britain.
O306-4549/78/iOO1-O305502.00/~
ACHIEVEMENTS OF THE D R A G O N PROJECT C. A. Rennie* Chief Executive, April 1959 - July 1968
A b s t r a c t - - T h e D r a g o n High T e m p e r a t u r e Reactor ( H T R ) Project b e g a n
1 April
1959 u n d e r
OECD auspices.
a l l o w e d the p r o j e c t
to c o n t i n u e
100 m i l l i o n d o l l a r s
under
ment.
The reactor
with double
from
corrosion
from
dimensional
were
easily solved.
to c o a t e d p a r t i c l e
proved
easy
changes
elements
fuel elements
maintenance.
of h e a t e x c h a n g e r s
an d
in the r e f l e c t o r
graphite.
circuit
t h a t k e p t the
steel These
p i p e s an d problems
operation were very
th e s o u n d n e s s of t h e c o n c e p t .
The Dragon
to be a v e r y u s e f u l t e s t b e d f o r a n u m b e r
HTR fuel element
an d c o n t i n -
Some difficulties
stainless
S o m e t e n y e a r s of e x p e r i m e n t a l
s u c c e s s f u l and d e m o n s t r a t e d reactor
purged
manage-
c o o l a n t in a h i g h l y c o n t a m i n a t e d
c o o l a n t a c t i v i t y low and p e r m i t t e d arose
a t a t o t a l c o s t of n e a r l y
evolved from
helium
containment,
17 y e a r s
in t i m e an d b u d g e t
e f f i c i e n t and f l e x i b l e i n t e r n a t i o n a l
design
uously decontaminated
Extensions
of d i f f e r e n t
concepts. INTRODUCTION
The Dragon ture
Reactor
1976.
Project,
or more
three
of e i g h t y e a r s
Present
Address:
formally
b e g a n on 1 A p r i l
The original agreement
y e a r s , but a f t e r period
Project,
years
between
a revised
up to 1967,
Wareham,
the OECD High T e m p e r a -
1959 an d e n d e d on 31 M a r c h the S i g n a t o r i e s
agreement
was
was for five signed for a
w i t h i n a b u d g e t ofo~25 m i l l i o n .
Dorset, 305
England.
306
C. A. Rennie This latter a g r e e m e n t w a s of three years each,
subsequently extended three times for periods
m a k i n g a total of seventeen years and a total
budget of just unda~r¢~49 million (about i00 million dollars). In discussing the a c h i e v e m e n t s to be a n s w e r e d would from
seem
of the Project the m a i n questions
to be whether the Project w a s
a success
the technical point of v i e w and whether the Signatories to the
a g r e e m e n t got value for their m o n e y .
However,
before discussing this
it is relevant to look back to the position of nuclear energy s o m e twenty years ago w h e n
the Project w a s
first proposed.
the climate for nuclear energy projects w a s first nuclear p o w e r
Undoubtedly
very different then.
The
stations had been constructed and s o m e had already
given good p e r f o r m a n c e . future of nuclear p o w e r
There were seemed
difficulties but the c o m m e r c i a l
very bright and there w a s
great en-
t h u s i a s m for exploring different reactor types to find out w h i c h would be the best. In E u r o p e
in particular there w a s
a desire to initiate a joint
project not only because it should be advantageous economically but also because
it w o u l d d e m o n s t r a t e the international nature of nuclear
energy r e s e a r c h and development.
Light water
carbon dioxide cooled reactors w e r e The
already in the c o m m e r c i a l
s o d i u m cooled fast breeder reactor w a s
national basis so that the choice w a s vanced water m o d e r a t e d reactor or a m o r e
cooled reactors and
being developed on a
virtually limited to a m o r e
a d v a n c e d gas cooled reactor, using h e l i u m cooling.
and successful collaboration w a s
the D r a g o n
ad-
reactor such as the aqueous h o m o g e n e o u s
In any event,the h e l i u m cooled high t e m p e r a t u r e
projects in the U S A
phase.
later established with the national
and G e r m a n y .
Project w a s
reactor w a s chosen,
It is w o r t h recalling that, w h e n
started, the reactor s y s t e m w a s
envisaged
as one with fission product emitting fuel, a very active h e l i u m circuit, and with a clean up plant w h i c h would hopefully r e m o v e neutron absorbing fission products. Reactor E x p e r i m e n t
of the
The initial design of the D r a g o n
( D R E ) w a s b a s e d on these assumptions. ORGA
The
some
NIZ A TION
technical objectives of the Project w e r e
specified in the re-
307
Achievements of the Dragon Project vised a g r e e m e n t
and are given in .Appendix I to this paper as it is
against these objectives that the w o r k However,
before discussing the technical side, it is worth looking at
the organization of the Project. Project,
of the Project m u s t be judged.
which w a s
the Signatories, management It w a s
In fact, the first achievement
not due to its o w n
was
of the
efforts but to the w i s d o m
to have been set up within a workable
of
and efficient
and administrative f r a m e w o r k . laid d o w n
that all legal acts,
including the placing of con-
tracts,
should be carried out by the Signatory of the host country,
namely
the UK.AE.4,
acting on behalf of the Project,
clearly stated that the Project w a s UK.AE.A
Purposes
Committee,
the responsibility of the
of M a n a g e m e n t
on which each Signatory w a s
.A key provision of the a g r e e m e n t w a s seconded
to the Project f r o m
and its General represented.
that staff should be
their current e m p l o y e r
bursed for their services f r o m
Project funds.
who was
career prospects.
that the budget of the Project w a s period of years,
Another key provision w a s
set, not annually,
agreed by the B o a r d
the Signatories then paid the agreed a m o u n t s
These
from
of pension
but over a
initially eight years and latterly over three years.
The annual expediture w a s
all p a y m e n t s
reim-
This provision m e a n t
that the Project did not have to get involved in p r o b l e m s funds and long t e r m
also
completely independent of the
or any other individual signatory,
Chief Executive being to the B o a r d
but it w a s
of M a n a g e m e n t
and
into a separate account,
this account being authorized b y the Project.
provisions enabled the Signatories to k n o w
exactly w h e r e
they stood at all times as regards
Project funding and assured t h e m
that no over-spend w a s
O n the other hand, the s a m e
possible.
visions enabled the Project to plan a p r o g r a m knowing that funds would be m a d e
staff, and hence
than expected,
Of course,
savings had to be m a d e
could quickly be m a d e
or increase the n u m b e r
staff costs w a s
within the $greed total budget.
of years
available within a agreed total amount.
The facility of being able to decrease seconded
over a n u m b e r
pro-
a major
factor in keeping
if one p r o g r a m
elsewhere,
of
cost m o r e
but such changes
by the Project through the B o a r d
of M a n a g e m e n t .
308
C. A. Rennie REACTOR The DRE
was
based
DESIGN
initially on the use of fission product emitting
fuel with a highly radioactive helium coolant circuit and this accounts for such features of the design as P u r g e d fuel elements Provision of a very c o m p r e h e n s i v e fission product r e m o v a l Gas
helium purification and
system
bearing circulators with no rotating seals
Only one small (about l-ft diameter) entry to the pressure An
machine
flange
vessel
elaborate fuel handling procedure
discharge
removable
with a charge and
inside the pressure
vessel and a fuel
handling cell outside A
leak-tight double containment
While the reactor w a s under ing fuel w a s
structure.
construction,
fission product
retain-
developed and later used for the reactor but it was
too late to change the basic design of the reactor.
However,
then
the
original design concept proved to be extremely useful as it m a d e possible,
among
of m e a s u r e m e n t s major
other things,
it
to carry out a very detailed p r o g r a m
on fission product release and deposition.
fault in the original design concept w a s
T h e only
in the heat r e m o v a l
s y s t e m which gave considerable trouble later on due to excessive corrosion on the water The
side of the p r i m a r y
heat exchangers.
reactor operated very satisfactorily over its ten-year life
and the m a i n
problems
that w e r e
encountered and successfully dealt
with were: Oscillation and bowing power
of the control rods,
swings and s o m e
causing
sticking of the rods which w a s
cured by fitting suitable d a m p i n g
restraints on articulated
rods. Replacement
of the inner reflector graphite blocks which
had b o w e d
due to irradiation effects.
Corrosion
of the p r i m a r y
heat exchangers
which was
cured by correcting the water treatment procedures, modifying the gas inlet p l e n u m
to avoid hot spots caused
309
Achievements of the Dragon Project by channeling of the hot inlet gas,
and reducing flow
instabilities in the boiler tubes. Removal
of identification tape containing polyvinyl
chloride, which w a s
causing stress corrosion on small
stainless steel pipes. Correcting the first two p r o b l e m s charge m a c h i n e
as a general purpose
these functions perfectly. charge m a c h i n e contractors.
was
manipulator
one of the achievements was
operated for the next 13 years It would,
Another
was
inside the pressure
however,
have needed 1976,
some
vessel without any maintenance
if
as the positional accuracy
not as good as it had been.
achievement
of the Project and its contractors w a s
gas bearing
circulators which gave
problems.
It w a s
tube bundles w e r e
the
14 years use without any m a j o r
possible to r e m o v e
intervals and in fact it w a s changer
of the Project and its
installed in the reactor in 1963 and
the Project had been extended beyond of the m a c h i n e
and it p e r f o r m e d
In fact, the behavior of the charge dis-
The m a c h i n e
maintenance.
involved using the charge dis-
and inspect the circulators at
necessary
to do this w h e n
changed.
The
the heat ex-
successful carrying out of
these operations without having to resort to expensive and timeconsuming
decontamination
procedures
virtues of the high temperature
reactor.
REACTOR The was
OPERATION
original timetable proposed
to c o m m e n c e
can be counted as one of the
in 1958 before the Project started
detailed design and construction of the D R E
1959 with construction essentially complete m i d - 1962,
and operation at p o w e r
construction w o r k achieved
in August
in m i d -
and criticality achieved by
beginning in mid- 1963.
In practice
did not start until early 1960 and criticality w a s 1963.
Operation at p o w e r
1965 with full operation in April 1966. about two years late on the p r o g r a m
began in the middle of
The D R E
was,
therefore,
envisaged at the start of the
Project. A b o u t one year of this delay w a s starting the w o r k
due to initial difficulties in
such as obtaining the right staff, placing the m a j o r
C. A. Rennie
310
contracts and setting up the proper organization, while the other year was
due to over o p t i m i s m about the time needed.
H o w e v e r , on balance
it can be counted a real a c h i e v e m e n t of the Project to have got thus far in the first 7 years of its life, bearing in m i n d that the p r o g r a m of r e s e a r c h and d e v e l o p m e n t w o r k ment
studies w a s
fact, in t e r m s
on fuel and materials and on assess-
progressing very favorably at the s a m e
of timescale the progress
of the D r a g o n
time.
In
Project c o m p a r e s
favorably with that for other national projects on high temperature
re-
actors. One
of the objectives of the Project w a s
to demonstrate the
feasibility of operating a reactor using a high pressure h e l i u m circuit.
cooling
It v,as s h o w n that welds p r o d u c e d by standard m e t h o d s w h i c h
passed the conventional radiographic and ultrasonic tests w e r e tight and r e m a i n e d leak tight.
Similarly O-ring
valves and high quality gasket joints w e r e the required p e r f o r m a n c e . testing procedures,
leak
seals, bellows sealed
all s h o w n to be capable of
With economically sensible design and
leakage f r o m
in trivial h e l i u m losses f r o m
a large reactor plant should result
the point of view of cost and of contami-
nation levels. Another
important p r o b l e m
high purity h e l i u m and it w a s with m o l y b d e n u m
is that of m o v i n g parts operating in s h o w n that selected materials lubricated
disulphide p e r f o r m e d well.
or frequently used m e c h a n i s m s
However,
all c o m p l e x
are best sited in cooler zones w h e r e
oil and grease contamination is negligible so that conventional lubricants can be used.
It w a s
found during m a i n t e n a n c e w o r k
actor e x p e r i m e n t that no difficulties w e r e mating
on the re-
encountered in dismantling
surfaces even in hot zones of the reactor such as the piston
ring seals on the nimonic hot ducts.
Helium
seems
to be an ideal
coolant gas for reactors on the basis of experience with the D R E . T h e effective heat transfer properties and f r e e d o m f r o m
corrosion
effects have been k n o w n for a long time and experience s h o w s that good design can o v e r c o m e One
problems
of lubrication and of leakage.
of the uses of a reactor e x p e r i m e n t that has good instrumen-
tation is to investigate the transient behavior of the reactor system. Many
tests of this type w e r e
carried out and the following e x a m p l e s
Achievements of the Dragon Project
311
illustrate the effects of reducing and increasing coolant flow with no movement
of the control rods.
speed and hence m a s s
With a slow reduction of circulator
flow the p o w e r
while the gas outlet temperature perature falls slightly.
output reduces
rises slightly and the gas inlet tem-
Increasing the circulator speed to its f o r m e r
value returns the reactor to its n o r m a l The test.
rate at w h i c h p o w e r
It w a s
operating conditions.
can be increased w a s
found that an increase
in p o w e r
obtained in about 5 seconds with changes temperature. mass
correspondingly
T h e nuclear p o w e r
studied in another
of about 15%
could be
of less than 5 ° C
response
in fuel
lags behind the coolant
flow increase but this is covered by the release of stored heat
f r o m the graphite in the core.
These
and m a n y
other tests d e m o n -
strated the practicability of control by coolant flow for both steady state and p o w e r
following conditions. FUEL
Numerous
studies were
which consists discuss
entirely
made
mentioning
provided for tests in l o o p t e s t s system
reactor.
available
of t h e p r i m a r y
reactor
over
fission product particles graphite retains
matrix fission
transparent
to f i s s i o n
of p a r t i c l e s
in p r o p e r t i e s
provides
is a d i f f u s i o n b a r r i e r
:lamaged by o p e r a t i o n number
of y e a r s ,
matrix
products
products.
the r e v e r s i b l e
purge out
dependence
a real double
containment.
at n o r m a l
of f i s s i o n
of
conditions, inherent
products
The
temperatures,
is m o r e
Although coated particles
adverse
by t e s t s
T h e f u e l c o n c e p t of c o a t e d
which,
i n v o l v ed and t h e i r
the r e l e a s e
out
significant
w a s to c o n f i r m ,
but at high t e m p e r a t u r e s
under
to c a r r y
to f a i l w i t h o u t p r o d u c i n g
on t e m p e r a t u r e .
in a g r a p h i t e
experiment
d i f f i c u l t to c a r r y
was possible
to
However,
of the f u e l e l e m e n t
of the P r o j e c t
a number
release
Because
core,
circuit.
O n e of t h e a c h i e v e m e n t s in t h e
w h i c h the r e a c t o r
if r e q u i r e d , i t
expected
is n o t s p a c e
in d e t a i l in t h i s p a p e r .
which would have been very
on f u e l w h i c h w a s
contamination
work
of t h e r e a c t o r
but t h e r e
th e o p p o r t u n i t i e s
in a n o t h e r
which was
of th e b e h a v i o r
of f u e l e l e m e n t s ,
the fuel d e v e l o p m e n t
it is w o r t h
tests
AND M A T E R I A L S
or less m a y be
because
of t h e l a r g e
statistical
variability
into the
c o o l a n t is s l o w
C. A. R e n n i e
312
but
progressive.
checks
and
However,
on
shut-down
reducing
of the
the
reactor
fuel
and
graphite
temperature
stops
the
release
of fission
feature
was
products. A good demonstration by a high 1250°C sively the
was
reactor
only
experimental
the
release
removed
slightly
the
irradiation
period
On another
cause
set was
a maximum
and
the
element
problems
correctly.
The
fuel
the
reactor
for
the
reactor
experiment
the
deposition
of fission
be.
when
Even
fission was
found
deposited formly
that
or was
of t h e support
pass
any
structure
would
confirmed
circuit clamps
was
observed
were
life
cells
with
no
set in
that
of the
expected
helium
to
where circuit
products
exchanger
shut
operation
conditions
fission
the
normally
the
3
serious
then
it was
into the
for
was
demonstrated
under
which
until
were
problem
the heat
gags
reactor
In fact,
run
design
during
examination
evidence
and
it
were not uni-
The
reactor
in the its
reactor
ten-year
compo-
life and which
on the helium
effects use
experiment,
of components
of d a m a g e
the possible
not detectable.
of t h e
deterioration
occurred
and
for
circuit.
appreciable
significant
was
operated
The
gags
life.
conservative
have
flow
and behaved
condensible
by the detailed
No
flow
emitted
gas
of
fuel
reactor
2000oc,
located.
not the
through the
the
in the
and
of a b o u t
were
of the
around
that
removed.
of fuel
all
reactor
ten-year
was
on shut-down
equipment
coolant
to the hot
design
its
progres-
increases.
reloaded
deliberately
of the fairly
unlikely
nents
were
first
distributed
it was
this
nearly
on the
In view
over products
were
the
was
was
set
with
coolant
of its
samples
products
the
element rest
large
into
removed
and
failed
at
b e l o w 10 - 4 . In this -Z 10 over the 80-day
to
element
activity
to operate
and when
limit
temperature
coolant
fuel
contamination
fuel
Yet
provided
133 w a s
sudden
loaded
expected
the handling
steadily
a fuel
as
stopped
normal
xenon
no
designed
of 80 d a y s .
reactor
increased
occasion
of t h e h i g h
down
for
but with
incorrectly with
the
fuel
and
coolant
The
ratio
ratio
1800°C
into the
contaminated.
experiment
days
at
mentioned
in which
period
from
release-to-birth
were
run
the
was
above
experiment
deliberately
over
element
the
temperature
of t h e
of the
of fretting reactor
side
on various experiment
313
Achievements of the Dragon Project for fuel testing m e a n t from
some
individual channels.
helium streams there w e r e
h e l i u m outlet gas t e m p e r a t u r e s of up to 9 5 0 ° C There was
affecting the nimonic liners of the outlet ducts, but
no obvious signs of d a m a g e
tion w h i c h w a s
the possibility of these hot
made
when
from
the reactor w a s
the superifical e x a m i n a -
shut down.
GENERAL CONSIDERATIONS The
easy m a i n t e n a n c e
of any reactor is of p r i m a r y
importance
to the operator because of the high ratio of capital to operating costs. In this respect the h e l i u m cooled reactor is almost unique as the inert nature of the coolant m a k e s the circuit m u c h
more
the prediction of activity levels in
reliable c o m p a r e d
to reactors with chemically
active coolants such as water or carbon dioxide. DRE
in c o m m o n
Pebble B e d
with that for the P e a c h
B o t t o m reactor and the A V R
reactor has confirmed that n e w
in the p r i m a r y
Experience with the
standards of low activity
circuit can be achieved.
In practice the w o r s t difficulties in p r i m a r y usually c o m e
circuit m a i n t e n a n c e
f r o m deposited activity arising either f r o m fission pro-
ducts or activated materials transported round the circuit and the behavior of such deposits is often unpredictable.
In a h e l i u m cooled
reactor the generation of any corrosion products is reduced e n o r m o u s l y by the inert nature of the coolant and the fairly high t e m p e r a t u r e around the circuit m e a n s
that m o s t fission products plate out in the
coolest part of the circuit such as the heat exchanger tubes and circulator impellers.
One
of the m o s t
encouraging features w a s
highly adherent nature of any activity because
the
it w a s deposited on clean
metal surfaces rather than on easily detached corrosion products. general only very simple m e a s u r e s of activity f r o m
components
were
needed to prevent any spread
or e q u i p m e n t r e m o v e d
f r o m the reactor,
such as the use of plastic bags or sheeting, but in m o s t activity could be r e m o v e d It is n o w
some
sign,
cases such
by wiping with a cloth.
fifteen years
particle fuel, w h i c h w a s
In
since tests w e r e
an entirely n e w
b e g u n on coated
concept of fuel element de-
only really possible with h e l i u m cooling.
Progress
in this n e w
field has b e e n very encouraging indeed and fuel of this type is n o w
314
C. A. Rennie very m u c h
a practical possibility as is evidenced by the Fort St.Vrain
and the A V R
power
not so m u c h
The
In fact, the p r o b l e m s
those arising f r o m
might arise f r o m the p r i m a r y
reactors.
normal
operation,
which r e m a i n are
but those which
the accidental ingress of air or water vapor
helium circuit.
safety a r g u m e n t s
will, of course,
for future high temperature
power
Such factors are the use of a fuel element
withstanding very high temperatures strophic failure,
reactors
depend on the detailed design of the reactor but they
can be based on factors which have been demonstrated elsewhere.
into
and
capable of
for long periods without cata-
the slow temperature
the low level of p r i m a r y
in D R E
response
to p o w e r
transients,
circuit activity and contamination,
and the
ease of detecting helium leakage. The
main
safety hazard
dation and water
is the possibility of excessive
gas production,
of the helium p r i m a r y
resulting f r o m
core oxi-
simultaneous failures
circuit and the boiler tubes.
However,
there
is every reason to expect that proper design of the prestressed
con-
crete pressure vessel and of the boiler circuits will enable acceptable safety a r g u m e n t s
to be put forward
of single failures are very m u c h REA CTOR
in this unlikely case.
Other cases
easier to deal with. ASSESSMENT
In the course of the life of the Project several reactor assessment
studies w e r e
carried out both on the u r a n i u m
the low e n r i c h m e n t u r a n i u m
fuel cycle.
The
235 thorium,
and
engineering features of
the reactor are largely independent of the fuel cycle and resulted in designs within a prestressed
concrete pressure
flow through the reactor core and u p w a r d pods around the core.
The
vessel with d o w n w a r d
flow through the boilers in
concept of podded boilers inside the pre-
stressed concrete pressure vessel w a s
first proposed by the Project
and has been a feature of later designs of gas cooled reactors elsewhere. The main
difference between the various designs of high t e m p e r a -
ture reactor has been in the kind of fuel element proposed.
While
all the proposals are based on the use of coated particles in a graphite
Achievements of the Dragon Project matrix,
both the geometrical a r r a n g e m e n t
specified have been different. posed as one w a y
315
and the type of coating
T h e pebble bed type of reactor w a s pro-
of simplifying the fuel handling p r o b l e m s
type of reactor is being actively studied in the G e r m a n
and this
national pro-
gram. The
earlier studies in the Project w e r e
based on using a prismatic
type of fuel with the actual fuel carried in graphite tubes in a graphite block,
the core of the reactor consisting of a n u m b e r
these graphite blocks.
At the s a m e
element being considered w a s and fuel holes in it.
time in the U S A
of stacks of the basic fuel
a graphite block with both coolant holes
In practice,
the D R E
was
sufficiently versatile
to be able to test to a certain degree all three basic types of fuel and latterly it w a s
generally agreed that for the prismatic
reactor fuel
the preferred type should be the graphite block with fuel and coolant holes in it. With regard to coated particles the simplest type is the B I S O particle with two distinct layers of pyrolytic carbon coating but the TRISO
particle with an additional silicon carbide layer between the two
carbon layers w a s now
also studied extensively in the Project.
a very considerable a m o u n t
and p e r f o r m a n c e
There
is
of data available about the fabrication
of these coated particles to assist the reactor de-
signers in specifying the fuel element for a p o w e r
reactor.
Different
fuel cycles require different heavy metal densities in the fuel bodies and it is mainly in this area that w o r k
is continuing,
so that full ad-
vantage can be taken of the potential of coated particle fuels. Besides the use of the high temperature steam
cycle generating plant,
Project,
studies w e r e
reactor with a conventional also carried out by the
both on direct cycle gas turbine p o w e r
heat applications.
A
program
of w o r k
plants and on process
to investigate materials,
would be suitable for the higher gas temperatures 1000oc
or m o r e ,
the Project w a s
was
started but w a s
by no m e a n s
envisaged,
which
of
complete w h e n
terminated. CONCLUSION
In this short account of the achievements
AXE 5 : 8
10
o
of the D r a g o n
Project
316
C. A. Rennie it has not been possible to cover everything and even the points that have been dealt with, have only been treated rather superficially. This is not so surprising w h e n izing seventeen years w o r k during its life.
The
of a Project which achieved a great deal
seventeen A n n u a l Reports of the Project have
been published by the O E C D the w o r k
of the Project.
in Paris, In addition,
of the Project over the whole shortly as D r a g o n detail all the w o r k
one is in effect reviewing or s u m m a r -
and cover in considerable detail a technical review of the w o r k
seventeen-year
Project Report
i000,
period will be published
and this report will cover in
referred to in this paper and very m u c h
more
besides. However,
it is possible to list s o m e
of the achievements
of the
Project during its life of seventeen years. I. from,
The
international nature of the Project in no w a y
and in m a n y
out the w o r k Z.
ways
it w a s
enhanced,
detracted
the ability of the Project to carry
asked to do.
The experience
the right m a n a g e m e n t
of the Project s h o w e d
and administrative
that it is possible with
structure to have a viable
and successful Project which can be easily controlled financially and can,
if necessary, 3.
be terminated in an orderly m a n n e r .
T h e need to invite tenders
to ensure that contracts w e r e difficulties.
The
widely distributed did not cause undue
O n balance the Project gained both f r o m
view of cost and delays f r o m 4.
in all the Signatory countries and
the point of
this international competition.
objectives of the Project w e r e
stage and the Project m a n a g e m e n t
was
clearly defined at every
given adequate authority to
carry out its tasks with simple procedures
for obtaining rapid authori-
zation for planning and executing its p r o g r a m . 5.
N o particular difficulty w a s
the international t e a m
at the A t o m i c
experienced
in the integration of
E n e r g y Establishment at Win-frith,
and a considerable esprit de corps quickly sprang up and has been maintained. 6.
Although the actual operation of the D R E
two years later than originally planned,
at p o w e r
was
this delay is c o m p a r a b l e
some to
that often occurring in national projects and probably arose for the
317
Achievements of the Dragon Project same
reason,
namely
over o p t i m i s m
in the very early stages of the
Project. 7.
The actual operation of the D R E
very successful,
apart f r o m
the serious loss of operating time caused
by failures in the heat exchangers, operation.
T h e s e failures w e r e
gained w a s
not relevant to p o w e r
fit w a s
the experience
and r e p l a c e m e n t 8.
The
during the first four years of
just a nuisance as the experience reactors and the only positive bene-
and confidence gained in reactor maintenance
of components.
results of the fuel and materials p r o g r a m
pressive but difficult to s u m m a r i z e , confirmed
that there s e e m
area for p o w e r 9.
The
temperature
very im-
except £o say that the results in either
reactors. work
10 years ago which reactors.
that these ideas are Finally,
were
to be no insuperable p r o b l e m s
reactor a s s e s s m e n t
studies s o m e
ment
over the 10-year period w a s
set out the m a i n features of high
Subsequent w o r k
by industry has confirmed
still relevant today.
and in s o m e
of the D r a g o n
by the Project produced design
ways
Project,
perhaps
was
the m o s t
important achieve-
to s h o w that it w a s
possible to have
international collaboration and sharing of costs in an area of technology which
some
of the Signatories could not afford to do on their own.
The fact that the Project w a s ture p o w e r
terminated without a n e w high t e m p e r a -
reactor project being started in any of the Signatory
countries w a s
disappointing but due m o r e
to other factors than to any
failure of the Project in carrying out its p r o g r a m It s e e m s
fair to say that the a n s w e r
at the beginning of this paper Project w a s
a success f r o m
tories to the a g r e e m e n t
of work.
to the two questions posed
can be given as 'yes'.
The D r a g o n
the technical point of view and the Signa-
did get value for their m o n e y . APPENDIX
I
A n n e x to Revised Project A g r e e m e n t (The Signatories to this A g r e e m e n t France,
Germany,
w e r e Austria, Belgium, D e n m a r k ,
Italy, L u x e m b o u r g ,
Switzerland and the United K i n g d o m )
Netherlands,
Norway,
Sweden,
C. A. Rennie
318
Technical outline of Joint P r o g r a m m e I.
The original objectives of the joint prograrnrne w e r e twofold:
the
carrying out of a progranu-ne of research and development w o r k in the field of high temperature gas cooled reactors, and the design, construction and operation of a reactor experiment to translate the results of this research and development w o r k into practical experience of this type of reactor.
These objectives have governed the w o r k which w a s carriedout
in the period Ist April 1959 to 31st M a r c h 1962. 2.
A n additional objective of the prograrnzne f r o m ist April 196Z,
is to provide the Signatories with information leading to the design of an economic,
land-based, gas cooled, carbon moderated,
high temperature
power reactor. The a i m will be to acquire sufficient knowledge and experience over the period ending 31st M a r c h 1967, to f o r m the basis for the design and construction of a large power station. Preliminary reference designs will be prepared as early as possible. The potentialities of power reactor systems using either fission product emitting fuels or fission product retaining fuels will be considered. 3.
The prograrnrne f r o m ist April 1962, comprises the following
broad area:a. Completion of design and construction work, followed by commissioning and operation of the reactor experiment. b. R e s e a r c h and development w o r k concerned both with the additional objective, and including m o r e basic w o r k needed to guide longer-term developments. c. W o r k on the development,
fabrication and irradiation of
fuel elements and the materials used in them, including post- irradiation examination. d. A s s e s s m e n t work, reference designs, and design studies for large power reactor systems. 4. The reactor experiment will be brought into operation as soon as possible, information on day-to-day running will be compiled and the behavior of components will be analyzed.
The experimental p r o g r a m m e
operations will be planned so as to obtain the m a x i m u m
for
amount of informa-
tion which will be applicable to large power reactor systems.
Types of
319
Achievements of the Dragon Project fuel elements which e m e r g e f r o m the early assessment studies and f r o m fuel development w o r k will be tested in the reactor, the m o s t promising types being tested in conditions as close as possible to those which will obtain in a large power reactor. 5. The research and development p r o g r a m m e
will include:-
a. Reactor physics and theoretical studies, including experiments utilizing the reactor experiment,
and the interpretation of
these results. b. Completion of the present w o r k in the field of heat transfer, including the seven-element experiment. c. Continuation of w o r k on development of components,
and
studies in the bearing shaft seal and gas bearing fields. d. Continuing studies on m a s s transfer and coolant processing. e. Studies of compatibility problems affecting high temperature reactors, and investigations of techniques such as high temperature m e a s u r e m e n t
applicable to these reactors.
f. R e s e a r c h of a m o r e fundamental nature necessary for longer t e r m development will also be undertaken,
largely through
external contracts with national research centres and other institutes. This p r o g r a m m e
will include studies on the
behavior of fission products in carbon, graphite and carbon bodies, the characteristics of possible fuel element materials and fuel bodies, and the factors determining the reactivity of materials with impurities which m a y be found in the helium coolant. 6.
]Emphasis will be given in the research and development
programme
to the development of the graphite and the fuel compacts
needed for fuel elements.
Both fission product retaining fuels andfission
product emitting fuels will be investigated.
Irradiation experiments will
be carried out both in the reactor experiment and elsewhere together with the necessary post-irradiation examination.
Estimates will be m a d e of
the cost of fuel element fabrication, reprocessing and refabrication. 7.
The assessment work, which is an additional objective of the
Project, will include:-
C. A. Rennie
320
a. T h e o r e t i c a l s t u d i e s , i n c l u d i n g r e a c t o r p h y s i c s , h e a t t r a n s f e r f l u i d flow. b. E n g i n e e r i n g s u r v e y s a n d r e f e r e n c e d e s i g n s t u d i e s . c. T h e p l a n n i n g a n d i n t e r p r e t a t i o n of e x p e r i m e n t a l w o r k a n d t e s t s r e l a t i n g to (a) a n d (b) u s i n g the f a c i l i t i e s a v a i l a b l e to the P r o j e c t ,
i n c l u d i n g the r e a c t o r e x p e r i m e n t .
d. D e v e l o p m e n t of p r e l i m i n a r y
r e f e r e n c e d e s i g n s as e x p e r i e n c e
is a c c u m u l a t e d b o t h f r o m the r e s e a r c h programme
and development
a n d f r o m the o p e r a t i o n of the r e a c t o r
experiment.
e. E c o n o m i c s u r v e y s b a s e d u p o n the f o r e g o i n g s t u d i e s a n d u p o n t h e g e n e r a l e x p e r i e n c e g a i n e d b y the P r o j e c t in the h i g h temperature
field.
8. I n a d d i t i o n to the w o r k c a r r i e d out a t W i n f r i t h a n d u n d e r c o n t r a c t w i t h o t h e r o r g a n i z a t i o n s in the S i g n a t o r i e s ' c o u n t r i e s , tion arrangements
suitable coopera-
m a y be m a d e w i t h o t h e r o r g a n i z a t i o n s w o r k i n g in the
same high temperature
gas cooled reactor field.
In t h i s w a y , the b e n e f i t
of the e x p e r i e n c e of o t h e r s in t h i s f i e l d c a n be b r o u g h t to b e a r on the w o r k of the P r o j e c t .