Cradle-to-gate sustainable target value design: integrating life cycle assessment and construction management for buildings

Cradle-to-gate sustainable target value design: integrating life cycle assessment and construction management for buildings

Accepted Manuscript Cradle-to-Gate Sustainable Target Value Design: Integrating Life Cycle Assessment and Construction Management for Buildings Sarah ...

1MB Sizes 237 Downloads 226 Views

Accepted Manuscript Cradle-to-Gate Sustainable Target Value Design: Integrating Life Cycle Assessment and Construction Management for Buildings Sarah V. Russell-Smith, Michael D. Lepech PII:

S0959-6526(15)00265-6

DOI:

10.1016/j.jclepro.2015.03.044

Reference:

JCLP 5312

To appear in:

Journal of Cleaner Production

Received Date: 2 April 2014 Revised Date:

9 March 2015

Accepted Date: 13 March 2015

Please cite this article as: Russell-Smith SV, Lepech MD, Cradle-to-Gate Sustainable Target Value Design: Integrating Life Cycle Assessment and Construction Management for Buildings, Journal of Cleaner Production (2015), doi: 10.1016/j.jclepro.2015.03.044. This is a PDF file of an unedited manuscript that has been accepted for publication. As a service to our customers we are providing this early version of the manuscript. The manuscript will undergo copyediting, typesetting, and review of the resulting proof before it is published in its final form. Please note that during the production process errors may be discovered which could affect the content, and all legal disclaimers that apply to the journal pertain.

ACCEPTED MANUSCRIPT

1

Cradle-to-Gate Sustainable Target Value Design: Integrating Life Cycle Assessment and

2

Construction Management for Buildings

3

Sarah V. Russell-Smith and Michael D. Lepech

5

Department of Civil and Environmental Engineering

6

Stanford University, Stanford, CA, United States

7

e−mail: [email protected]

SC

9

Abstract

Building stakeholders cannot easily quantify the environmental impacts of buildings as

M AN U

8

RI PT

4

they accrue during construction. The goal of this work is to demonstrate a method to measure

11

and manage the cradle-to-gate life cycle environmental impacts by linking environmental targets

12

with modern construction management methods, to enable buildings to meet sustainable target

13

values (STV). In this work, a construction activity-based computational framework was

14

developed to enable stakeholders to reliably and efficiently construct cradle-to-gate life cycle

15

models capturing environmental impacts including carbon and energy associated with material

16

extraction, manufacture, transport to site, and construction. These models allow stakeholders to

17

measure and manage impact accrual so as to not exceed STVs; without this framework,

18

construction managers and other building stakeholders do not possess adequate environmental

19

management tools to deliver projects consistently at or below STV. Specifically, the components

20

developed are: (1) time dependent impact accrual budgets during construction and (2) impact

21

measurement during construction. These benchmarks are used to determine whether a specific

22

project is above or below target values, similar to methods for cost and schedule variance

23

analysis. Two case studies were used to test this framework. This integration provides a life

AC C

EP

TE D

10

1

ACCEPTED MANUSCRIPT

24

cycle assessment (LCA) modeling platform for management of environmental footprint during

25

construction.

26

Keywords

28

Life Cycle Assessment; LCA; Sustainable Target Value; STV; Construction Management;

29

Sustainable Building

RI PT

27

32

1. Introduction

In the United States, the building sector is responsible for approximately 41% of primary

M AN U

31

SC

30

energy consumption and 40% of greenhouse gas emissions, while also contributing to

34

acidification, eutrophication, smog, and solid waste emissions (U.S. EIA, 2011). Despite

35

environmental concerns associated with energy consumption and greenhouse gas emissions, the

36

US Department of Energy (DOE) projects that primary energy consumption and greenhouse gas

37

emissions associated with buildings are expected to grow by 13% and 6% by 2020, respectively.

38

(U.S. EIA, 2011). This increase is in stark contrast to the fossil fuel based reduction proposed by

39

the Architecture2030 Challenge in order to avoid expected average global temperature increases

40

between 2.0ºC and 2.4ºC (stabilized atmospheric CO2e between 445-490ppm) (IPCC, 2007).

41

Architecture2030’s timeline, which starts with a 70% reduction in 2015 and reaches a 100%

42

reduction in 2030, combined with the fact that 75% of the built environment in the US will be

43

new or renovated in the next quarter century (Architecture2030, 2011), represents an opportunity

44

to create a less environmentally impactful building infrastructure.

45 46

AC C

EP

TE D

33

Environmental impacts associated with buildings accrue throughout the life cycle phases of material extraction, transport to site, construction, use, and demolition. The cradle-to-gate

2

ACCEPTED MANUSCRIPT

impacts associated with buildings – those from material extraction, manufacturing, transport to

48

site, and onsite construction – are often ignored. This is due to poor measurement methodology

49

availability and the fact that they have historically been outweighed by operational impacts.

50

Because these impacts have constituted a smaller proportion of life cycle impacts, literature has

51

focused on reducing operational impacts and emission of harmful substances to the environment.

52

However, these cradle-to-gate impacts are nontrivial and become a larger percentage of a

53

building’s total life cycle impacts as the use phase impacts decrease due to more efficient

54

systems, onsite electricity generation, etc. (Faludi and Lepech, 2012). In the case of net-zero

55

operational energy buildings, the cradle-to-gate impacts can represent the majority of impacts

56

(Thiers and Peuportier, 2012). Construction managers need to be included in the sustainability

57

discussion so that these cradle-to-gate impacts are effectively managed and reduced (Shen et al.,

58

2010). In order to create environmentally sustainable buildings, the impacts of buildings at each

59

stage of their life cycle, not just operation but including cradle-to-gate, must be quantified.

SC

M AN U

TE D

60

RI PT

47

In order to manage these impacts, the methodology must include both measurement and a standard or target by which to establish what is ‘sustainable.’ Sustainable target value (STV)

62

design has been recently proposed by Russell-Smith et al. (2015a; 2015b). The STV design

63

methodology requires setting targets for environmental metrics such as global warming potential

64

and primary energy for the life cycle of a building and using the STV software to predict design

65

performance relative to these targets. The cradle-to-gate research presented in this paper

66

describes a methodology to construct a building to meet a sustainability target. It operationalizes

67

STV design by providing a process by which to develop sustainability budgets (or targets) for

68

construction and to measure and manage the actual environmental impacts accrual during

69

construction.

AC C

EP

61

3

ACCEPTED MANUSCRIPT

70

This work leverages life cycle assessment (LCA) and pre-existing construction management and control techniques. Together, these tools can provide a robust tool for

72

modeling, measurement, and tracking of environmental impacts during the construction phase of

73

a building life cycle to meet STVs. Specifically, the research integrates LCA with construction

74

management methods in order to facilitate prediction, budgeting and control of environmental

75

impacts of building materials, transport, and construction. The goal of this work is the

76

development of a method to set quantitative environmental cradle-to-gate budgets and to

77

measure and manage the accrual of cradle-to-gate environmental impacts over the course of

78

construction.

M AN U

SC

RI PT

71

79 80 81

1.1 Sustainable Target Value (STV) Design

STV design, which has been developed by Russell-Smith et al. (2015a; 2015b), provides a method to reduce the environmental impacts of buildings throughout their life cycle by setting

83

targets for environmental indicators and giving design teams the tools to explore building design

84

performance as early as the design phase. The targets are set based on the ecological limit state or

85

carrying capacity of the earth as defined by science and policy experts. For example, the global

86

warming potential (GWP) and primary energy targets are based on scientific analysis performed by

87

the Intergovernmental Panel on Climate Change (IPCC). The ozone depletion potential (ODP) and

88

potable water targets are based on the Montreal Protocol and United States Energy Policy Act of

89

2005, respectively. In short, if buildings are designed to meet the STV targets, these performance

90

levels could theoretically be supported by the planet’s resources indefinitely. The STV target-setting

91

methodology is generalizable; STV targets can be established for any environmental indicator for

92

which a limit state has been defined.

AC C

EP

TE D

82

4

ACCEPTED MANUSCRIPT

93

The STV methodology combines life cycle assessment (LCA) and target value design (TVD) to rapidly produce more sustainable building designs. By establishing site-specific

95

sustainability targets, this STV research has demonstrated that buildings can be designed to perform

96

at higher environmental standards than those designed without a target in place. Results show that

97

STV design implementation yielded building designs that met or surpassed the target in terms of

98

environmental performance. However, designing to a target does not guarantee actual performance

99

at or below the STV. To actually deliver a constructed facility that meets the STV design requires

SC

RI PT

94

tools and methods to measure and manage impact accrual in real-time. With current techniques, this

101

environmental impact accrual measurement is not possible. As a result, cradle-to-gate impacts are

102

often ignored or estimated. This work proposes and demonstrates a novel framework, adapting

103

current construction management techniques and integrating LCA, to construct a facility with a

104

verified impact accrual profile that delivers on STV design.

M AN U

100

106

TE D

105

1.2 Life Cycle Assessment Approach for Analyzing Building Impacts LCA is an internationally standardized method of accounting for all inputs, outputs, and

108

flows within a process, product, or system boundary to accurately quantify a comprehensive set

109

of environmental, social, and economic indicators (Cucek et al., 2012; Finnveden et al., 2009). It

110

considers all of the phases in a process, product, or system’s life, from raw material extraction,

111

processing, transportation to site, installation, to use, removal, and recycling or disposing. For

112

built environments, these different stages include the raw material extraction for the different

113

assembly components of the building (i.e. limestone mining and calcination for cement), the

114

manufacturing, transport to site, construction and installation, the building’s operational life,

115

maintenance and retrofitting, and at the end of life, its demolition.

AC C

EP

107

5

ACCEPTED MANUSCRIPT

The international framework for conducting an LCA prescribes four stages, which

117

include (1) definition of goal and scope, (2) life cycle inventory (LCI) analysis, (3) impact

118

assessment, and (4) interpretation (U.S. EPA, 2012; ISO, 2006a; ISO, 2006b). The definition of

119

goal and scope stage establishes the intended application and audience (goal), as well as the

120

functional unit (reference basis for calculating inputs and outputs), system boundaries and life

121

cycle phases for analysis (scope). In the LCI analysis, the relevant inputs and outputs for a given

122

product or system are identified and quantified throughout its life cycle. The impact assessment

123

stage evaluates the magnitude and significance of the product's or system’s environmental

124

impacts based on the LCI analysis. Lastly, conclusions and recommendations are drawn from the

125

results based on the two previous stages. The purpose of the interpretation is to identify the

126

major burdens, impacts, and potential areas for impact reduction.

SC

M AN U

127

RI PT

116

Numerous LCA studies have investigated the sustainability impacts of constructed facilities; to date, most have found that operational impacts dominate life cycle impacts

129

(Gambatese and Rajendran, 2005). Junnila at al. (2003, 2006) and Scheuer et al. (2003) found

130

that for commercial structures, over 90% of life cycle energy consumption and the majority of

131

carbon dioxide emissions stem from the use phase of the building. For residential structures,

132

Keoleian et al. (1993) found that most impacts occur during the use phase. In a comprehensive

133

review of 16 other studies, Sartori and Hestnes (2007) found significant impacts throughout the

134

life cycle of constructed facilities, with strong correlation between total life cycle energy

135

consumption and operating energy consumption.

EP

AC C

136

TE D

128

Yet, even as operational impacts have historically dominated building life cycle impacts,

137

the cradle-to-gate impacts are not insignificant. Blanchard and Reppe (1998), Keoleian et al.

138

(2001), and Faludi and Lepech (2012) have examined residential structures that use highly

6

ACCEPTED MANUSCRIPT

energy efficient materials and building operation technologies, and have found that such

140

technologies push impacts from the use phase onto the material production and construction

141

phases. As building operation becomes more efficient and net-zero energy use buildings become

142

more mainstream, the relative percentages of embodied impacts of materials and onsite

143

construction impacts will grow (Mequignon et al., 2013; Peuportier et al., 2013). Further, studies

144

show that the embodied impacts increase for these net zero buildings due to factors such as

145

increased insulation, material and manufacturing intensive PV panels, and specialized

146

construction techniques required for novel systems (Gustavsson and Joelsson, 2010, Thiers and

147

Peuportier, 2012). Construction produces large environmental impacts that need to be measured

148

and managed (Bilec et al., 2007; Ochoa et al., 2002; Sharrard et al., 2007). The limited

149

construction phase specific research has focused primarily on construction waste management

150

and off road vehicle emissions (Franklin Associates, 1998). There is a need to further quantify

151

the environmental impacts of onsite construction activity.

SC

M AN U

TE D

152

RI PT

139

LCA has been demonstrated as a useful tool for products including buildings and has been found to be valuable for quantified environmental management and for isolating which components

154

and phases are most impactful (Basbagill et al., 2013; Guinee et al., 1993; Jeswani et al., 2010). This

155

paper introduces a LCA methodology that can be used to determine a building project’s cradle-to-

156

gate impacts and to quantify which materials and activities are most impactful. The goal is to enable

157

not only measurement but also management of sustainability impacts during construction by

158

tracking the impacts associated with individual construction activities. From a cost perspective,

159

construction management and project control methods are well-established for monetary

160

measurement and management. This paper presents a parallel method, for environmental impacts,

161

combining methods of construction management and control.

AC C

EP

153

7

ACCEPTED MANUSCRIPT

162 163 164

1.3 Construction Management and Project Control Methods In this study, construction management and project control methods form the basis of the methodology into which LCA and STV are integrated. Construction management and project

166

control methods are well-developed and widely accepted for construction cost management

167

(Barrie et al., 1984; Carr, 1993; Clark et al., 1978; Rasdork et al., 1991). Effective, ongoing

168

monitoring is a basic requirement for tracking and managing cost, time, and quality on a

169

construction project. Project control ensures progress by measuring actual completion of work

170

and comparing it to planned work. Analysis of the project’s underperformance in terms of

171

schedule, price, and level of quality leads to updated forecasts, which signify the need to take

172

corrective actions. Important components of effective project controls include the early (planning

173

phase) definition of appropriate scope breakdowns, useful performance metrics, a management

174

scheme for measuring and reporting of performance, as well as accurate performance forecasting

175

(De Marco et al., 2009; Ritz, 1994).

SC

M AN U

TE D

176

RI PT

165

Construction processes are modeled for costing, scheduling, and planning based on individual construction activities. A key first step is identification of these activities. The

178

construction industry, distinct from many other industries, has well-designed methods for

179

decomposing the complexity of major multi-year projects into fundamental work items and tasks

180

for use in detailed cost and schedule tracking (Winch, 2002). In order to do this, a work

181

breakdown structure (WBS) is created based on MasterFormat to serve as the basis for progress

182

measurement (Jung et al., 2004). MasterFormat is a widely used standard in the construction

183

industry in the United States and Canada to format specifications for construction contract

184

documents. Once the WBS and activities have been established, a construction schedule is

AC C

EP

177

8

ACCEPTED MANUSCRIPT

prepared based on an activity precedence network. Each activity is assigned a duration, and the

186

resources necessary for its execution are allocated at the activity start time. The project must be

187

monitored and actual progress compared to the pre-determined schedule in order to control it.

188

Many methods exist for monitoring effort and work completion. These methods include direct

189

contact with an observer at the site, employee time cards, feedback from time-lapse photography

190

for estimating project completion, checklists, and bar charts (Abeid et al., 2002).

Similar methods are transferrable to environmental impact control. Whereas tools for

SC

191

RI PT

185

high fidelity environmental impact control and process monitoring are limited, economic cost

193

controls are highly developed and form the foundation of current construction management and

194

operation practices. Variance from budgeted costs or schedules, whether positive or negative, is

195

managed by construction superintendents to effectively meet predetermined cost and schedule

196

targets. In order to methodically manage the reduction of environmental impacts of built

197

facilities, it is necessary to link environmental goals with modern activity-based construction

198

management methods. Time dependent impact budgets (like cost budgets) provide the basis for

199

such project control. Specifically, two components are used: (1) time dependent impact accrual

200

predictions for the construction phase, and (2) actual impact measurement during construction.

201

Predicted impact accrual is compared to actual impact accrual as a benchmark for whether the

202

project is above or below expectations, similar to a cost and schedule variance analysis.

204 205

TE D

EP

AC C

203

M AN U

192

2. The Framework: Activity-Based Environmental Management for STV In this research, LCA is integrated with construction management schedule variance

206

analysis in order to facilitate the construction of sustainable buildings and deliver constructed

207

facilities that meet STV design goals. In parallel to creating predicted and measured cost curves

9

ACCEPTED MANUSCRIPT

with the goal of keeping the construction project under a specified monetary target, the new

209

objective is to leverage these tools to create environmental impact accrual curves with the goal of

210

keeping the project under a specified environmental target set using STV design. This

211

methodology gives building stakeholders a basis for continuous management and environmental

212

impact control throughout the construction process.

213

RI PT

208

The scope of the LCA includes the inputs to and outputs from the building construction, beginning with the extraction of the raw materials needed to assemble the building and ending

215

with the completion of the construction activities. As such, an accurate and meaningful

216

quantification of impacts will depend on a detailed understanding of the construction activities.

217

These activities, and their temporal order, are determined based on the construction schedule and

218

the precedence network.

M AN U

SC

214

The construction schedule is used to determine the timing of system and material

220

processes, which are inextricably linked to quantifiable environmental impacts. The LCI for each

221

of these activities serves as the link between activity and impact. A given activity’s LCI includes

222

the material (including the processing actions to take raw material from extraction to finished

223

product), any transportation systems to bring the materials to the construction site, and the

224

construction processes involving equipment or material use onsite. Human laborers are not

225

included as part of the construction activities inventories; their commute transportation system

226

use and their lunch consumptions, among other examples of impact, are out of the scope.

227

Electricity used for jobsite trailers and lighting are also excluded.

EP

AC C

228

TE D

219

Performing the detailed LCI analysis for each of the individual construction activities in

229

the schedule serves as the necessary precursor to evaluating their impacts. The materials and

230

processes that make up each activity are determined. These materials and processes are then

10

ACCEPTED MANUSCRIPT

modeled in an LCA software tool (in this case Pre’s SimaPro and the EcoInvent v2.2 database

232

(EcoInvent, 2010)) as individual materials and processes, but grouped into construction activities

233

for analysis. This process makes it possible to determine which activities are environmentally

234

impactful. It is important to highlight this distinction, which represents a departure from typical

235

LCA. The analysis presented herein groups materials and processes into activities within the

236

LCI, so that they are fully integrated with activity-based scheduling and management used in

237

construction. Further, this method allows for investigation into material and process pieces

238

constituting the activities to make specific proactive substitutions to reduce impacts.

SC

There are a variety of impact assessment methods for conducting the impact assessment

M AN U

239

RI PT

231

of an LCA. For the purpose of this research, the EcoIndicator 95 method was used to compute

241

values for target environmental indicators, which include global warming potential (GWP),

242

primary energy consumption, acidification potential, eutrophication potential, and carcinogenic

243

emissions. EcoIndicator 95 was chosen to allow direct comparison to several other building LCA

244

studies that have used the EcoIndicator 95 method.

245

TE D

240

Once the activities have been evaluated for these indicators and before construction begins, the predictive curve of impact accrual over the construction phase can be created. This is

247

shown in Figure 1. This curve illustrates the forecasted impact accrual versus time and is called

248

the budget impact line (BIL). This step involves linking activity scheduling with impacts to

249

produce cumulative impact functions over time. This link was used to create activity-based

250

construction environmental impact budgets. For each activity, it is assumed that the impacts

251

accrue linearly over the completion of the activity. For instance if 100 MJ primary energy is

252

associated with producing and placing concrete and the activity duration is 4 days, 25 MJ are

253

attributed daily. Once construction begins, the real time measurement of environmental impacts

AC C

EP

246

11

ACCEPTED MANUSCRIPT

(based on physical rental agreements and work item logs) allows for the creation of the actual

255

impact curve, called the actual impact line (AIL), which is shown in Figure 1. The AIL is

256

compared to the benchmark prediction (BIL) as the project continues. This comparison provides

257

a quantified indication of performance with regards to environmental metrics and progress

258

towards the overall environmental targets and projected impact budgets. The results from the

259

preceding steps are used to manage the accrual of environmental footprint (e.g., CO2e, SOx, etc.)

260

over the course of construction, analogous to construction cost control. The notable differences

261

from cost control lie in the need for more detailed material, transportation, and equipment use

262

information. Figure 1 shows a sample footprint accrual for a hypothetical construction project

263

over time.

M AN U

SC

RI PT

254

265 266 267

AC C

EP

TE D

264

Figure 1. Schematic View of Impact Accrual Versus Time

BIL represents the budgeted impact accrued during construction. AIL represents actual

268

impact accrued during construction. The dashed vertical line marks the end of construction.

269

Implementing existing cost variance control management techniques, this type of figure is used

270

to measure construction processes and facility operations in real-time to better ensure that

12

ACCEPTED MANUSCRIPT

environmental performance targets are met. AIL and BIL are analogous to cost variance figures

272

prevalent in the construction industry for project cost management. From Figure 1 it can be seen

273

that at 50% completion, the actual impacts are less than the budgeted impacts. Thus, the project

274

is either below environmental budget or behind schedule on construction completion. Based on

275

this information, a construction manager can look at the schedule to determine the case and make

276

adjustments if necessary. From Figure 1, at 75% completion, measured impacts are greater than

277

predicted impacts, thus the project is either ahead of schedule or above environmental budget.

278

Again, further investigation allows for determination of the case and for adjustments to be made.

279

Potential adjustments include sourcing more local materials, fuel switching in equipment,

280

reducing machinery idling time, streamlining of equipment activities, and increasing recycling

281

and reuse of materials.

M AN U

SC

RI PT

271

282

284

3. Case Studies

TE D

283

The framework discussed in the preceding section enables building stakeholders to quantify both budgeted and accrued environmental impacts in an effort to deliver STV designed

286

buildings. Two case studies were conducted to demonstrate this framework; an infrastructure

287

project and a building project. These case studies were selected to demonstrate the generality of

288

the framework in two different project types within the construction industry. While the

289

infrastructure case study evaluates only the framework for impact budgeting (BIL), the building

290

project case study incorporates both the budgeted (BIL) and accrued (AIL) impact lines.

AC C

291

EP

285

To conduct the inventory analysis for each study, material quantities, equipment types

292

and usage, and transportation distances were collected and/or calculated. This process involved

293

quantity takeoffs from construction documents for the infrastructure case study and quantity

13

ACCEPTED MANUSCRIPT

takeoffs from a BIM model and from conversations with the general contractor and

295

subcontractors for the building case study. Construction drawings (hard copies) were used to

296

determine the dimensions and quantity takeoffs for the infrastructure case. The BIM model, in

297

combination with PDFs of structural drawings, was used to calculate the material quantities for

298

the building case. RS Means MasterFormat crews were used to determine the equipment

299

requirements. Hours of equipment usage were calculated using material quantities and RS Means

300

productivity data.

SC

301

RI PT

294

For each case study, an individual activity’s materials and processes were modeled into an LCA software database (the EcoInvent (2010) database housed within SimaPro) as an

303

assembly by finding analogous materials and processes in existing or newly created LCI

304

databases. In instances where an exact match did not exist for the material or process, an

305

approximation or assumption was made. Details for materials, equipment, and transport methods,

306

along with assumptions made for each of the two case studies, are provided below.

309

TE D

308

3.1 Infrastructure Project Case Study

The first case study was an infrastructure project involving the rehabilitation of a steel

EP

307

M AN U

302

girder bridge in southwest Michigan. The bridge is located on state highway M-89 where it

311

crosses the Kalamazoo River between Heath and Valley townships. It is a 2-lane vehicle bridge

312

with a reinforced concrete deck and spans 110 meters. The project, Michigan Department of

313

Transportation Project BHT 9903002, included partial demolition of the existing structure and

314

bridge deck and addition of structural steel and new reinforced concrete decking. The specific

315

construction activities, materials, and equipment are described below.

AC C

310

316

14

ACCEPTED MANUSCRIPT

317 318

3.1.1 Goal and Scope Definition The goal of the infrastructure project LCA was to test the activity-based LCA framework. A budget impact line (BIL) for this project was retrospectively calculated based on the

320

completed construction documents. The project scope included the following activities: (1)

321

concrete deck hydrodemolition, (2) placement of concrete overlay, (3) strengthening of steel

322

girders by adding plate steel, (4) replacement of guardrail, (5) asphalt paving, (6) epoxy painting,

323

(7) excavation, (8) removal of old drainage structures, and (9) installation of replacement

324

drainage structures. The construction activities were determined from the general plan notes of

325

the construction documents package. The documents included a summary of the project,

326

technical notes on work to be done, and 2D renderings of the bridge and work. An example of

327

how an activity was developed is described in the inventory analysis discussion. This

328

infrastructure case was chosen based on the limited number and scope of activities and

329

availability of construction documents and data.

330

332

3.1.2 Inventory Analysis

The material types were taken from the construction document descriptions and labels.

EP

331

TE D

M AN U

SC

RI PT

319

The material quantities were calculated based on length, area, and volume dimensions given on

334

the drawings. Each activity identified above was matched with a corresponding MasterFormat

335

activity and construction equipment was determined based on the crew listed. Only equipment

336

use was included; human laborers were excluded from the analysis. For example, for the

337

hydrodemolition activity, the 146 m3 of concrete to be demolished was determined based on the

338

length, width, and depth provided on the construction drawings. The only material input required

339

was water. The corresponding MasterFormat code used was 030505100010 for selective

AC C

333

15

ACCEPTED MANUSCRIPT

concrete demolition, excluding saw cutting, torch cutting, loading and hauling. The crew for this

341

code is B9 which includes a 250 CFM air compressor and a 60 pound pavement breaker. The

342

equipment and materials were modeled in the LCA software, SimaPro, to determine the

343

associated impacts: water was modeled as ‘water, deionized at plant’ and the compressor and

344

pavement breaker were modeled as ‘diesel, burned in building machine.’ In this case, there are

345

no materials transported to site, so transport is omitted. Summing the impacts from materials,

346

transport, and equipment provides the total impact for this activity. For hydrodemolition,

347

material impacts are 2.0x103 kg CO2e and equipment impacts are 3.7x106 kg CO2e. The total

348

activity impact is divided by the duration (in days) to determine impact of an activity per day.

349

For hydrodemolition, the global warming impacts per day are 9.5x104 kg CO2e. Table 1 below

350

shows the material quantities associated with the bridge rehabilitation project.

SC

M AN U

351

RI PT

340

Table 1. Materials and Quantity Infrastructure Project

TE D

Material

352 353

AC C

EP

Bitumen Concrete Epoxy Coating Formwork, Plywood Grout Iron, Sand Casted PVC Pipe Reinforcing Steel Riprap Sand Structural Steel Timber Water

Unit

Quantity

kg m3 kg kg kg kg kg kg tonne kg kg m3 kg

68,025 146 8,646 548 194,580 844 63,950 7,929 1,000 768,800 154,416 0.3 2,616,933

3.1.3 Impact Assessment

354

Based on all the construction activities performed, the total impact of the designed work,

355

in terms of life cycle GWP and primary energy consumption, was 4.4x106 CO2e and 7.2x107 MJ 16

ACCEPTED MANUSCRIPT

(lower heating value), respectively. These totals include embodied impacts of materials, impacts

357

from transporting materials to site, and impacts of onsite construction. Combining material,

358

transportation and construction equipment impacts for each activity, project impacts were

359

associated with specific tasks. The breakdown of activities and impacts is shown in Table 2.

RI PT

356

Table 2. Construction Activities and Budgeted Impacts for Infrastructure Project

Totals

Duration (Days) 39 3 2 2 12 5 1 3 1

GWP (CO2e) 3.7x106 5.7x103 1.8x105 4.4x104 3.3x105 5.6x104 3.1x102 3.3x104 1.2x104

58*

4.4x106

Energy (MJ LHV) 5.9x107 1.1x105 4.3x106 7.1x105 1.7x106 1.2x106 1.9x103 3.7x106 2.1x105

Acidification (kg SO2) 4.8x104 7.6x101 9.2x102 3.1x102 1.6x103 1.9x102 6.9x10-1 4.9x102 7.6x101

Eutrophication (kg PO4) 8.5x103 1.4.101 7.5x101 9.1x101 1.6x102 3.0x101 1.5x10-1 3.6x100 2.6x101

Carcinogens (kg B(a)P) 7.6x10-2 1.8x10-3 2.2x10-4 1.8x10-2 6.6x10-3 3.0x10-3 9.2x10-6 7.1x10-4 4.6x10-3

7.2x107

5.2x104

8.9x103

1.1x10-1

SC

Construction Activity Hydrodemolition Excavation Drain Structure Structural Steel Concrete Overlay Epoxy Painting Curb and Gutter Paving Guardrail

M AN U

360

362 363

3.1.4 Interpretation

TE D

*Total duration is not a sum of all activity durations because work on some activities occurs simultaneously.

361

Linking the activities shown in Table 2 with the construction schedule, accrual of environmental impacts can be plotted versus percent project completion. Theoretically, these

365

links allow construction managers to pinpoint sources of impact and focus process

366

improvements. This time-dependent budget for environmental impacts can be coupled with the

367

Gantt chart to illustrate impact accrual over the course of activity completion (Figure 2).

AC C

EP

364

17

M AN U

SC

RI PT

ACCEPTED MANUSCRIPT

368

Figure 2. Gantt Chart and Impact Variance Budget for Infrastructure Project

370

This tool provides a simple visualization of impact accrual and can guide project

TE D

369

management during the construction phase. Further, when coupled with plots of actual accrual of

372

impacts, it can inform project management and decision-making. This retrospective

373

infrastructure case demonstrated that the activity-based LCA framework is feasible. To further

374

investigate construction activity-based LCA as an impact management and control tool, a case

375

involving both actual (AIL) and budgeted (BIL) impact lines was required. Therefore, a second

376

case was undertaken focusing on a building erection project.

AC C

EP

371

377 378

3.2 Building Erection Case Study

18

ACCEPTED MANUSCRIPT

379

A building project involving extensive retrofitting and rehabilitation of a football stadium was chosen as a case study to compare budgeted and actual environmental impact lines for

381

selected construction activities. The project included work on the stadium structure and athletic

382

field. It involved extensive seismic upgrades as well as preservation of historic elements of the

383

original stadium structure. Activities associated with the construction of a new press box

384

building, which provides broadcast support spaces and a multi-functional club space, were

385

selected for this analysis. The structure is a seismic-resistant steel frame with glass and concrete

386

façade. The specific activities analyzed for this case study are those associated with the assembly

387

and erection of the structural steel for the press box. The methodology is scalable to the entire

388

project provided widespread adoption within the construction management team.

389

391

3.2.1 Goal and Scope Definition

The goal of this case study was to test the framework’s applicability in developing and

TE D

390

M AN U

SC

RI PT

380

comparing budgeted and actual environmental cradle-to-gate impacts. The activities include (1)

393

erecting crawler crane, (2) erecting structural steel and safety deck for Northern portion of press

394

box, (3) plumbing and aligning structural steel for Northern portion of press box, (4) bolting and

395

welding structural steel for Northern portion of press box, (5) erecting structural steel and safety

396

deck for Southern portion of press box, (6) plumbing and aligning structural steel for Southern

397

portion of press box, (7) bolting and welding structural steel for Southern portion of press box,

398

and (8) dismantling crawler crane. This project was chosen due to the detailed BIM model

399

associated with the project. This particular portion of the project was chosen because it is limited

400

in scope in terms of both number of activities and number of subcontractors. Further, the

401

subcontractors were responsive to requests for material and transport data. Finally, the scheduled

AC C

EP

392

19

ACCEPTED MANUSCRIPT

402

dates of the construction activities included changes due to weather, material, and other delays

403

but the actual activities remained the same.

404

406

3.2.2 Inventory Analysis

RI PT

405

Table 3 lists the predicted and measured material quantities for the above listed activities. The BIM model, bidding documents, and subcontractor agreements were used to determine

408

specific quantity takeoffs and associated material impacts. These sources were supplemented and

409

interpreted by the general contractor. Purchase orders, change orders, and interactions with the

410

general contractor and subcontractors provided the actual material quantities and associated

411

impacts (i.e. transportation impacts). In parallel with the infrastructure case, the activities were

412

matched with corresponding MasterFormat activities.

M AN U

413

SC

407

Table 3. Materials and Quantity Takeoffs for Building Project

415

Unit kg kg kg kg

Quantity Budgeted Actual 851,846 969,714 1,361 1,538 227 232 18,144 17,891

EP

414

TE D

Material Structural Steel for Columns and Beams Stainless Steel Bolts Steel Fasteners Steel for Decking

For each construction activity, budgeted impacts and actual impacts were calculated by associating the impacts of each construction activity with the construction schedule. The general

417

contractor provided the preliminary schedule and weekly updated schedules. The construction

418

impacts included the impacts associated with materials (listed above), transport, and onsite

419

equipment. Transport data was either provided by the subcontractor, general contractor, or

420

estimated based on material availability in region. The same transport methods were assumed for

421

the predicted and measured impact calculations. The project activities were associated with the

422

corresponding MasterFormat work codes. For predicted impacts, the MasterFormat data was

AC C

416

20

ACCEPTED MANUSCRIPT

used to determine which construction equipment was required and the productivity rate. Due to

424

insufficient and inaccurate data on which equipment was actually used onsite, MasterFormat data

425

was also used to calculate actual impacts. Combining material, transportation and construction

426

equipment impacts for each activity, project impacts were associated with specific tasks for both

427

predicted and measured scenarios.

RI PT

423

428

3.2.3 Impact Assessment

SC

429

The budgeted total impact of the work in terms of GWP and primary energy consumption

430

was 1.21x106 kg CO2e and 2.02x107 MJ (lower heating value), respectively. The actual total

432

impact of the work in terms of GWP and primary energy consumption was 1.38x106 kg CO2e

433

and 2.29x107 MJ, respectively.

M AN U

431

The budgeted impacts (used to generate BIL) associated with each construction activity

434

are shown in Table 4 for GWP, energy consumption, acidification, eutrophication, and

436

carcinogens. The measured impacts (used to generate AIL) associated with each construction

437

activity are shown in Table 5.

TE D

435

Construction Activity

EP

Table 4. Construction Activities and Budgeted Impacts for Building Project

438 439

GWP (kg CO2e)

Energy (MJ LHV)

Acidification (kg SO2)

Eutrophication (kg PO4)

Carcinogens (kg B(a)P)

3 12 12 12 12 12 12 3

7.15x100 6.03x105 2.96x10-1 2.68x103 6.03x105 2.96x10-1 2.68x103 4.29x100

1.28x102 1.01x107 4.21x100 2.14x104 1.01x107 4.21x100 2.14x104 7.66x101

6.28x10-2 2.26x103 1.42x10-3 1.40x101 2.26x103 1.42x10-3 1.40x101 3.77x10-2

8.23x10-3 1.38x103 2.36x10-4 8.52x10-1 1.38x103 2.36x10-4 8.52x10-1 4.94x10-3

4.21x10-7 1.26x10-1 1.42x10-10 1.24x10-4 1.26x10-1 1.42x10-10 1.24x10-4 2.53x10-7

AC C

Crawler Crane Erection Structural Steel Erection (N) Plumbing & Aligning (N) Bolting & Welding (N) Structural Steel Erection (S) Plumbing & Aligning (S) Bolting & Welding (S) Crawler Crane Dismantling

Duration (Days)

Totals

440

1.12x106 2.02x107 4.54x103 2.77x103 2.52x10-1 *Total duration is not a sum of all activity durations because work on some activities occurs simultaneously. 49*

21

ACCEPTED MANUSCRIPT

441

Table 5. Construction Activities and Actual Impacts for Building Project

Totals

444

GWP (kg CO2e)

Energy (MJ LHV)

Acidification (kg SO2)

Eutrophication (kg PO4)

Carcinogens (kg B(a)P)

3 14 10 10 10 10 10 3

7.15x100 6.85x105 2.96x10-1 2.99x103 6.85x105 2.96x10-1 2.99x103 4.29x100

1.28x102 1.14x107 4.21x100 2.38x104 1.14x107 4.21x100 2.38x104 7.66x101

6.28x10-2 2.56x103 1.42x10-3 1.56x101 2.56x103 1.42x10-3 1.56x101 3.77x10-2

8.23x10-3 1.57x103 2.36x10-4 9.49x10-1 1.57x103 2.36x10-4 9.49x10-1 4.94x10-3

4.21x10-7 1.43x10-1 1.42x10-10 1.39x10-4 1.43x10-1 1.42x10-10 1.39x10-4 2.53x10-7

37* 1.38x106 2.29x107 5.16x103 3.14x103 2.86x10-1 *Total duration is not a sum of all activity durations because work on some activities occurs simultaneously.

445 446 447

RI PT

Crawler Crane Erection Structural Steel Erection (N) Plumbing & Aligning (N) Bolting & Welding (N) Structural Steel Erection (S) Plumbing & Aligning (S) Bolting & Welding (S) Crawler Crane Dismantling

Duration (Days)

SC

Construction Activity

M AN U

442 443

3.2.4 Interpretation

Linking the activities shown in Table 4 with the approved contract construction schedule, accrual of environmental impacts was plotted versus time to produce the BIL. Linking the

449

activities in Table 5 with the updated schedule (of actual work completed), accrual of

450

environmental impacts was plotted versus time to produce AIL. Figure 3 illustrates the budgeted

451

(solid black) and actual (dashed grey) accrual of GWP plotted above the Gantt chart of budgeted

452

and actual schedule for the included activities.

AC C

EP

TE D

448

22

M AN U

SC

RI PT

ACCEPTED MANUSCRIPT

453

455

Figure 3. Gantt Chart and GWP Variance for Building Project

TE D

454

Figure 3 demonstrates that the accrual of measured and predicted impacts can be plotted together to illustrate variance between the two lines for environmental impacts (in this case

457

GWP). It shows that the measured scheduled start date of press box activities is after the

458

predicted date. This was due to a combination of weather, change orders, and design alterations.

459

Figure 3 also shows that total duration of press box related activities was compressed, resulting

460

in a steeper AIL vs. BIL; the purpose was to save time in order to get the remainder of the

461

project activities back on predicted schedule. The total measured impacts are over budget

462

compared to the budgeted impacts – this is due mainly to increases in the amount of structural

463

steel used. The actual structural steel used for the press box was 117,868 kg greater than the

464

budgeted steel due to a design change. The construction manager could use the tool to assess the

AC C

EP

456

23

ACCEPTED MANUSCRIPT

impacts of implementing impact-saving strategies. In this case, the construction manager

466

explored biodiesel blends, alternate concrete mixes, and scheduling priorities in order to shift the

467

AIL and stay closer to the budget. This visualization illustrates that environmental metrics can be

468

measured, and theoretically managed, in parallel to cost in traditional construction management.

469

This has the potential to be a useful tool for construction managers if measuring and managing

470

environmental impacts is implemented more widely in the construction industry.

RI PT

465

473

4. Discussion

The case study applications of STV for construction, the activity-based LCA framework,

M AN U

472

SC

471

demonstrate that the predicted LCA impacts of materials, transport, and construction can be

475

linked with the relevant construction activities. The building case shows that both budgeted

476

(BIL) and actual (AIL) impacts can be quantified and compared and have the potential to be

477

managed under this framework. Using both BIL and AIL provides a construction management

478

tool for environmental impact management. When coupled with the Gantt chart, they can help

479

visualize whether a project is ahead or behind schedule as well as above or below its

480

environmental budget. It is important that this methodology leverages accepted construction

481

management techniques already in place in the architectural, engineering, and construction

482

(AEC) industries; previous work shows that lack of knowledge and expertise about

483

environmental effects combined with lack of access to environmental data parallel to cost and

484

performance data limits stakeholders’ ability to achieve environmental performance objectives

485

(Keoleian, 1993).

486 487

AC C

EP

TE D

474

The case studies demonstrate that the methodology can be applied to budgets limiting carbon dioxide emissions or other environmental indicators. In the press box construction case,

24

ACCEPTED MANUSCRIPT

the budgeted impacts line (BIL) represents the budgeted accrual trend over the course of the

489

project and ends at a final impact value. This final value could be likened to the monetary budget

490

for a similar prediction of project cost. In either case, the performance of the final project – the

491

actual impact line (AIL) – should end at or below this value if the project was designed and

492

carried out as planned.

RI PT

488

The power of this methodology lies in the ability of the building stakeholders to set more

494

aggressive performance targets, or sustainable target values (STV), beyond those relating to cost

495

control and in providing a way to manage performance to actually meet the targets. Previously,

496

even with the goal of being sustainable, construction managers and other building stakeholders

497

had no way to manage or verify performance in real-time during design and construction. Using

498

the activity-based environmental management for STV framework, when provided with a

499

building STV such as an embodied carbon dioxide emissions limit, a construction project can

500

now manage the project such that the impacts of all of the activities accrue to a value within this

501

limit. Thus, cradle-to-gate impacts can be verified to STV design targets. This also provides an

502

avenue for future construction bidding based on both cost and environmental impact. When

503

construction then takes place, the ongoing LCA provides an indication of where the project

504

stands in relation to this goal at each construction phase.

M AN U

TE D

EP

This work extends the STV framework described in Russell-Smith et al. (2015a) beyond

AC C

505

SC

493

506

design and enables construction activity-based environmental management for STV. It

507

contributes a previously lacking methodology to operationalize STV and produce constructed

508

facilities with verified environmental profiles. Building to the STV facilitates the construction of

509

buildings that actually perform within the boundaries of the STV targets. The STV methodology

510

is used to break down the impacts into those from materials, transport to site, construction, and

25

ACCEPTED MANUSCRIPT

operation so that performance for each phase can be assessed and compared. This

512

operationalization of STV builds upon existing management and control techniques for cost. It

513

uses techniques common to building construction stakeholders, facilitating ease of adoption. This

514

work, building to STV, provides a basic methodology to manage the production of buildings

515

from cradle-to-gate with sustainable life cycle impacts.

516

518

5. Limitations

SC

517

RI PT

511

Several limitations exist in terms of the scope of this work. These limitations exist with respect to the lack of inclusion of the entire life cycle and with respect to the availability of data

520

for the case studies. These limitations are discussed in more detail below.

521

M AN U

519

From a life cycle standpoint, this work does not account for the full life cycle of a building; cradle to gate includes material extraction, material processing, transportation of

523

materials to site, and construction processes. Cradle-to-gate excludes operation and end-of-life.

524

The intent was to provide a method of quantifying the often ignored cradle-to-gate impacts.

525

However, the literature to date shows that the majority of environmental impacts of buildings

526

stem from the operation phase (Junnila et al., 2006; Keoleian et al., 2001). Minimizing the

527

cradle-to-gate impacts would not necessarily achieve operational energy savings. Further, the

528

end-of-life impacts of demolishing and reusing, recycling, or landfilling the components could

529

mean ignoring the complications of disposing of hazardous materials or remediation of site as a

530

result of pollutants. For instance, if asbestos-containing insulation is used in design and

531

construction, there are major health and environmental impacts that must be dealt with at end-of-

532

life. The activity-based cradle-to-gate life cycle assessment method was developed to address the

533

previously often ignored cradle-to-gate impacts and to provide a method for construction

AC C

EP

TE D

522

26

ACCEPTED MANUSCRIPT

stakeholders to understand and quantify impacts, leveraging tools methods with which they are

535

familiar. This framework is a compliment to existing LCA frameworks which focus on the other

536

life cycle phases. A consequence of the scope limitations of this work, is the opportunityfor

537

future work in integrating the various life cycle stage models into a holistic LCA model.

538

RI PT

534

In terms of limitations with the case studies, there were several challenges faced in the application of the activity-based LCA framework. The most problematic was the availability of

540

data. A detailed, complete BIM model can better provide a complete quantity takeoff and

541

schedule for development of budgeted impact lines (BIL). However, the architecture,

542

engineering, and construction (AEC) firms were unwilling to share these models in their entirety,

543

so data had to be obtained by sending requests to members of the general contractor’s BIM team

544

for the building case study. The other significant data availability challenge was the accurate

545

measurement of onsite equipment use. Up-to-date records of equipment rentals and usage were at

546

times inaccurate or unavailable. Another limitation of this work is the applicability of data; since

547

the LCI databases are largely populated with values from European or North American

548

manufacturers and transportation authorities, the data tends to lose geographic fidelity.

549

551

6. Conclusion

This paper presents a life cycle assessment (LCA) framework for management and

AC C

550

EP

TE D

M AN U

SC

539

552

control of environmental impacts of constructing a building or infrastructure facility to meet

553

sustainable target value (STV) design targets. It builds on existing construction management

554

techniques to produce a method of accounting, managing, and controlling environmental impacts

555

of construction projects. Coupling environmental impacts of construction activities determined

556

using LCA with construction schedules can successfully produce time-dependent environmental

27

ACCEPTED MANUSCRIPT

557

impact budgets that form the basis for management of variance between predicted environmental

558

impacts and measured environmental impacts of constructed facilities. This is demonstrated

559

using a case study of select construction activities from a larger construction project. The framework produces environmental impact accrual timelines facilitating improved

RI PT

560

sustainability-oriented project management during the construction of a facility and offers unique

562

analysis opportunities to examine the managerial tradeoffs between construction decisions. It

563

enables designers, contractors, and engineers to manage designed and actual environmental

564

impacts and make more informed decisions from cradle-to-gate in order to meet STV. Future

565

research will further develop tools necessary to track actual environmental emissions from onsite

566

equipment usage, explore integration of LCA and building information modeling, monitor actual

567

facility material consumption, and expand the breadth of activities used to demonstrate the

568

framework to meet STV design targets.

TE D

569

M AN U

SC

561

Acknowledgments

571

The authors would like to thank the National Science Foundation Graduate Research Fellowship

572

Program (NSF GRFP) and the National Defense Science and Engineering Graduate Fellowship

573

(NDSEG).

AC C

574

EP

570

575

References

576

Abeid J., Arditi D., 2002. Time-lapse digital photography applied to project management.

577

Journal of Construction Engineering and Management, 128(6), 530-535.

578

28

ACCEPTED MANUSCRIPT

579

Architecture2030, 2011. The 2030 Challenge. . Accessed

580

June 30, 2013.

581

Barrie, D., Paulson, B., 1984. Professional Construction Management. McGraw-Hill.

RI PT

582 583

Basbagill, J., Flager, F., Lepech, M., Fischer, M., 2013. Application of life-cycle assessment to

585

early stage building design for reduced embodied environmental impacts. Building and

586

Environment, 60, 81–92.

SC

584

M AN U

587 588

Bilec, M., Ries, R., Matthews, H.S., Sharrard, A.L., 2007. Example of a Hybrid Life-Cycle

589

Assessment of Construction Processes. Journal of Infrastructure Systems, 12(4), 207-215.

590

Blanchard, S., Reppe, P., 1998. Life Cycle Analysis of a Residential Home in Michigan, M.Sc.

592

Thesis, University of Michigan, Ann Arbor, MI, United States.

593

TE D

591

Carr, R., 1993. Cost, schedule, and time variance and integration. Journal of Construction

595

Engineering and Management, 119(2), 245-265.

597 598

AC C

596

EP

594

Clark, F., Lorenzoni, A., 1978. Applied cost engineering. Marcel Dekker, Inc.

599

Cucek, L., Klemes, J.J., Kravanja, Z., 2012. A Review of Footprint analysis tools for monitoring

600

impacts on sustainability. Journal of Cleaner Production, 34, 9-20.

601

29

ACCEPTED MANUSCRIPT

602

De Marco, A., Briccarello, D., and Rafele, C., 2009. Cost and Schedule Monitoring of Industrial

603

Buildings: Case Study. Journal of Construction Engineering and Management, 135(9), 853-862.

604

EcoInvent Centre, 2010. EcoInvent data v2.2. Swiss Centre for Life Cycle Inventories,

606

Dübendorf, 2010.

RI PT

605

607

Faludi, J., Lepech, M., 2012. Ecological Payback Time of an Energy-Efficient Modular Building.

609

Journal of Green Building, 7(1), 100-119.

M AN U

610

SC

608

611

Finnveden, G., Hauschild, M., Ekval,l T., Guinée, J., Heijungs, R., Hellweg, S., Koehler, A.,

612

Pennington, D., Suh, S., 2009. Recent Developments in Life Cycle Assessment. Journal of

613

Environmental Management, 91(1), 1-21.

TE D

614 615

Franklin Associates, 1998. Characterization of Building-related Construction and Demolition

616

Debris in the United States. U.S. EPA.

EP

617

Gambatese, J., Rajendran, S., 2005. Sustainable Roadway Construction: Energy Consumption

619

and Material Waste Generation of Roadways. In: 2005 Construction Research Congress, ASCE,

620

San Diego, CA, United States, 1-13.

AC C

618

621 622

Guinee, J., Heijungs, R., Udo de Haes, H., Huppes, G., 1993. Quantitative Life Cycle

623

Assessment of Products 1: Goal Definition and Inventory. Journal of Cleaner Production, 1, 3-

624

13.

30

ACCEPTED MANUSCRIPT

625 626

Gustavsson, L., Joelsson, A., 2010. Life cycle primary energy analysis of residential buildings.

627

Building and Environment, 42, 210-220.

RI PT

628

Intergovernmental Panel on Climate Change (IPCC), 2007. Climate Change 2007: Synthesis

630

Report, IPCC 4th Assessment Report.

631

SC

629

International Standards Organization (ISO), 2006a. Environmental management – Life cycle

633

assessment – Principles and framework ISO 14040.

M AN U

632

634 635

International Standards Organization (ISO), 2006b. Environmental management – Life cycle

636

assessment – Requirements and guidelines ISO 14044.

TE D

637

Jeswani, H.K., Azapagic, A., Schepelmann, P., Ritthoff, M., 2010. Options for broadening and

639

deepening the LCA approaches. Journal of Cleaner Production, 18, 120-127.

640

EP

638

Junnila, S., Horvath, A., 2003. Life-cycle environmental effects of an office building. Journal of

642

Infrastructure Systems, 9, 157-166.

643

AC C

641

644

Junnila, S., Horvath, A., Guggemos, A., 2006. Life Cycle Assessment of Office Building in

645

Europe and the United States.. Journal of Infrastructure Systems, 12, 10-17.

646

31

ACCEPTED MANUSCRIPT

647

Jung, Y., Woo, S., 2004. Flexible work breakdown structure for integrated cost and schedule

648

control. Journal of Construction Engineering and Management, 130(5), 616–625.

649

Keoleian, G., 1993. Application of Life Cycle Assessment to Design. Journal of Cleaner

651

Production, 1, 143-150.

RI PT

650

652

Keoleian, G., Blanchard, S., Reppe, P., 2001. Life Cycle Energy, Costs, and Strategies for

654

Improving a Single Family House. Journal of Industrial Ecology, 4, 135-156.

SC

653

M AN U

655 656

Mequignon, M., Haddou, H.A., Thellier, F., Bonhomme, M., 2013. Greenhouse gases and

657

building lifetimes. Building and Environment, 68, 77-86.

658

Ochoa, L., Hendrickson, C., Matthews, H.S.,2002. Economic Input-Output Life Cycle

660

Assessment of U.S. Residential Buildings. Journal of Infrastructure Systems, 8(4), 132-138.

661

TE D

659

Peuportier, B., Thiers, S., Guiavarch, A., 2013. Eco-design of buildings using thermal simulation

663

and life cycle assessment. Journal of Cleaner Production, 39, 73–78.

AC C

664

EP

662

665

Rasdork, W., Abudayyed, O., 1991. Cost and schedule control integration: Issues and needs.

666

Journal of Construction Engineering and Management, 117(3), 486-502.

667 668

Ritz, G., 1994. Total construction project management. McGraw-Hill.

669

32

ACCEPTED MANUSCRIPT

670

Russell-Smith, S., Lepech, M., Fruchter, R., Meyer, Y., 2015a. Sustainable Target Value Design:

671

Integrating Life Cycle Assessment and Target Value Design to Improve Building Energy and

672

Environmental Performance. Journal of Cleaner Production, 88, 43-51.

RI PT

673

Russell-Smith, S., Lepech, M., Fruchter, R., Littman, A. 2015b. Impact of progressive

675

sustainable target value assessment on building design decisions. Building and Environment, 85,

676

52-60.

SC

674

677

Sartori, I., Hestnes, A., 2007. Energy use in the life cycle of conventional and low-energy

679

buildings: A review article. Energy and Buildings, 39(3), 249-257.

M AN U

678

680

Scheuer, C., Keoleian, G., Reppe, P., 2003. Life Cycle Energy and Environmental Performance

682

of a New University Building: Modeling Challenges and Design Implications. Energy and

683

Buildings, 35(10), 1049-1064.

TE D

681

684

Sharrard, A., Matthews, H., Roth, M., 2007. Environmental Implications of Construction Site

686

Energy Use and Electricity Generation. Journal of Construction Engineering and Management,

687

133(11), 846–854.

AC C

688

EP

685

689

Shen, L.-y., Tam, V.W.Y., Tam, L., Ji, Y.-b., 2010. Project feasibility study: the key to

690

successful implementation of sustainable and socially responsible construction management

691

practice. Journal of Cleaner Production, 18 (3), 254-259.

692

33

ACCEPTED MANUSCRIPT

693

Theirs, S., Peuportier, B., 2012. Energy and environmental assessment of two high energy

694

performance residential buildings. Building and Environment, 51, 276-284.

695

United States Energy Information Administration (U.S. EIA), 2011. Annual Energy Review.

RI PT

696 697

United States Environmental Protection Agency (U.S. EPA), 2012. Life Cycle Assessment

699

(LCA).

SC

698

700

EP

TE D

M AN U

Winch, G.,2002. Managing construction projects. John Wiley & Sons.

AC C

701

34