Electrical Power and Energy Systems 105 (2019) 521–528
Contents lists available at ScienceDirect
Electrical Power and Energy Systems journal homepage: www.elsevier.com/locate/ijepes
Development of protective schemes for hybrid AC/DC low-voltage distribution system
T
⁎
Chul-Ho Noha, Chul-Hwan Kima, , Gi-Hyeon Gwonb, Muhammad Omer Khana, Saeed Zaman Jamalia a b
College of Information of Communication Engineering, Sungkyunkwan University, Suwon, Republic of Korea Yonam Institute of Technology, Jinju, Republic of Korea
A R T I C LE I N FO
A B S T R A C T
Keywords: Hybrid AC/DC low-voltage (LV) distribution system Low-voltage DC (LVDC) distribution system Power system protection Protective coordination Transient analysis
As the interest in DC-based power system increases, the low-voltage DC (LVDC) distribution system is gaining attention. Until now, however, the related studies and developments are still not mature to commercialize the system. This corresponds to the protection system as well. In fact, previous studies have dealt with protection schemes targeting only the LVDC distribution system although the system is closely influenced by the lowvoltage AC (LVAC) distribution system–hybrid AC/DC low-voltage (LV) distribution system. However, most literatures reporting the hybrid AC/DC LV distribution system do not focus on the protection scheme. Thus, in the work, the protective schemes for the hybrid AC/DC LV distribution system are developed and coordinated. The transient analysis on the events in both systems is first conducted; subsequently, the protection schemes for each system are developed. Finally, two proposed protection schemes are coordinated using the state diagram and their performances are verified through simulations using the electromagnetic transients program (EMTP).
1. Introduction CURRENTLY, DC-based power systems are gaining attention in distribution and transmission systems. This trend resulted from the development of power electronic converters, introduction of distributed generation (DG), and increase of digital loads. Therefore, researchers have conducted various studies to develop conventional power systems that can accommodate these changes. In particular, low-voltage DC (LVDC) distribution systems are still in the development stage because some challenges need to be resolved [1–3]. One of them is to develop novel protection schemes for the LVDC distribution system, considering the fault characteristic due to power electronic converters. In this regard, many studies have dealt with various protection issues. Refs. [1–4] studied the aspect that should become a priority in the protection scheme for DC faults. Based on the fault analysis, they have concluded that the protection scheme for DC faults can detect and isolate DC faults rapidly, primarily with the current derivative. Refs. [5–6] proposed the protective coordination for the LVDC distribution system, and [7–8] considered the interconnections with DGs. Additional topics such as the detection of high-impedance fault, current-limiter, and fault location are discussed in [9–12]. As reviewed, however, most protection schemes proposed in the existing literatures targeted only the LVDC
⁎
distribution system itself. In the case DC network is being coupled to an AC network, LVDC distribution systems are generally supplied through two conversion stages: a transformer and an AC/DC converter. In this regard, the lowvoltage AC (LVAC) distribution system for AC loads is on the upstream of the LVDC distribution system with respect to efficiency and cost. Such a hybrid AC/DC low-voltage (LV) system, called the hybrid AC/DC LV microgrid or hybrid AC/DC LV distribution system according to their topologies, have been studied in many literatures so far. However, the existing literatures rarely discuss the protection scheme for the hybrid AC/DC LV distribution system. Refs. [13–21] presents the methods to control power flow in a hybrid AC/DC LV system. The control schemes to improve the system power quality are discussed in [22–24]. Moreover, [25–28] proposed cooperative control schemes among converters in a hybrid AC/DC LV system. Moreover, the existing protection schemes for DC systems are not suitable for protecting the hybrid AC/DC LV distribution system. That is because they hardly consider the impacts by disturbance in the upstream AC systems. The work therefore proposes the protective schemes for the hybrid AC/DC LV distribution system based on transient phenomena by disturbance in both LVAC and LVDC distribution systems. And then, the performance is verified by simulations using the electromagnetic
Corresponding author. E-mail address:
[email protected] (C.-H. Kim).
https://doi.org/10.1016/j.ijepes.2018.08.030 Received 20 May 2018; Received in revised form 31 July 2018; Accepted 22 August 2018 0142-0615/ © 2018 Elsevier Ltd. All rights reserved.
Electrical Power and Energy Systems 105 (2019) 521–528
C.-H. Noh et al.
transients program (EMTP). The proposed protective scheme coordinates two protection systems for both LVAC distribution system and LVDC one. In this regard, each protection system adopts typical factors: current magnitude for LVAC distribution system and current derivative for LVDC one. Thus, the main contribution of this work is how to coordinate two protection systems by using new circuit breaker (CBIT) in front of an AC/DC converter, which is proposed on the basis of the transient analysis in this paper. Especially, the state diagram is applied to discriminate the operation of individual protection systems and coordinate them. This work achieves not only the protection of each distribution system similar to the conventional ones, but also assures the normal operation even under fault conditions of other distribution system. Especially, the protective weak point of the existing protection schemes for DC distribution system, which cannot protect some transient phenomena due to the events in LVAC distribution system, can be solved in this study as well. The remainder of this paper consists of four sections. In Section 2, the transient analysis performed according to the events in the LVAC and LVDC distribution system is discussed (LADS and LDDS stand for LVAC and LVDC distribution systems hereinafter). Section 3 proposes the protective schemes for the hybrid AC/DC LV distribution system and coordinates them. In this section, each protection scheme for both distribution systems is described initially. Subsequently, in Section 4, the performance of the proposed scheme is verified by simulations using the EMTP. Finally, conclusions are presented in Section 5.
Open state LADS
ACCB
AC load Transformer ACCB
AC load
~ =
RAC,line+LAC,line
=
AC/DC converter
=
iDC
CDC
Rfault
VS
-
Fig. 2. Current flow due to DC fault.
2.1. Transient analysis by events in LDDS This section presents the results of the transient analysis under the DC fault state and the DCCB opening state shown in Fig. 2, which shows the equivalent circuit of one phase in the LADS. When a fault occurs in the LDDS, the capacitor (CDC) in the AC/DC converter starts to discharge, resulting in a capacitive discharge current (iDC) along a series RLC path in Fig. 2 [31]. It has a very short time constant and contribute to high fault currents [32]. To prevent the semiconductor switches from being damaged, they are deliberately opened at that time. The manufacturers define its maximum overcurrent capability to be 2–3 times the nominal current during various milliseconds [29,33]. The current increases and decreases dramatically while the capacitor voltage (Vc) discharges, and is in the form of an underdamped sinusoidal current expressed by
iDC (t ) = e−(Req /2Leq) t A sin(ωt + α ),
(1)
where Req and Leq denote the equivalent values of resistance and inductance in a fault current loop, respectively. A represents the current magnitude and ω represents the resonant frequency. For reference, (1) is the modified form from the original one by using a formula of a trigonometrical function. Finally, α denotes the damping factor. The equation of voltage transients for VC can be expressed as integral form of (1) because it is directly related with the capacitive discharge current. The fault is contributed by both the energy stored in the line inductance (LDC,line) and the AC source immediately after Vc is fully discharged, causing the current flow through the AC/DC converter as shown in Fig. 2 [34]. The two currents can be respectively expressed by
iL (t ) = −IL0 e (−Req, L /2Leq, L)(t − tC )
(2)
is (t ) = Vs / R eq, S + (Is0−Vs / R eq, S ) e (−Req, S / Leq, S )(t − tC )
(3)
where IL0 and IS0 denote the initial value of the current resulting from the discharge of LDC,line and AC source, respectively. Req,L, Leq,L, Req,S, and Leq,S represent the equivalent values of resistance and inductance on the corresponding paths, respectively. In addition, VS means the AC input voltage level and tC represents the time when Vc is fully discharged. Since the semiconductor switches are opened, the anti-parallel diodes become the path for the currents, resulting in the diodes being damaged. Thus, the DC fault must be interrupted before Vc is fully discharged. Moreover, the DC fault adversely affects the LADS by a higher current and voltage sag. This means that the circuit breaker (ACCB) in the LADS could be opened if the DC fault is not interrupted quickly enough. Next, the DC fault is interrupted by opening the circuit breaker in the LDDS. Subsequently, two distribution systems are isolated from each other and the LADS can be normally operated with a smaller load current than that under the prefault state. This is because only the AC loads are supplied.
DC load
DC/DC converter
= DCCB
=
LDDS
LS Vc
LDDS
DCCB
AC/DC converter
+
The concept of a hybrid AC/DC LV distribution system is illustrated first in this section. A hybrid AC/DC LV distribution system includes an upstream LADS supplying the LDDS, as shown in Fig. 1. The hybrid AC/ DC LV distribution system includes a transformer and an AC/DC converter at the input terminals of the LADS and LDDS, respectively. The transformer plays role to supply LVAC power to LADS by stepping down input voltage level, but it is regarded as the ideal voltage source in this paper. On the other hand, the AC/DC converter is controlled using a pulse width modulation (PWM) technique used to rectify the AC voltage into a DC voltage. In particular, the AC/DC converter is to be protected in the development of the protective schemes for a hybrid AC/DC LV distribution system. Moreover, DC/DC converters are installed in front of DC loads, which is to transform voltage level to the required level by using a duty ratio control scheme. The two types of circuit breakers in Fig. 1 represent a mechanical circuit breaker for the LADS (ACCB) and a solid state circuit breaker for the LDDS (DCCB). The solid state circuit breaker is applied due to the requirements for rapid interruption of DC fault. The solid state circuit breakers have become valid options for protecting DC fault because of its fast operation speed while the mechanical circuit breaker has the limitation [29]. Last, it is adopted TN-S grounding system connected with the middle point of AC/DC converter. That is because the fault detection is easier in the TN-S grounding system than in IT one [30]. In addition, the target system has low possibility to be touched by human contrary to telecom power systems or the system of customer-end.
Utility
After Vc discharges RDC,line+LDC,line
2. Transient analysis in hybrid AC/DC LV distribution system
LADS
While Vc discharges
DC load
Fig. 1. Concept of a hybrid LV distribution system. 522
Electrical Power and Energy Systems 105 (2019) 521–528
C.-H. Noh et al.
Current by VS
LADS
Open state
Current by discharge of CDC
AC/DC converter
Current flow under AC temporary fault
LDDS
AC/DC converter
LADS
LDDS RDC,line+LDC,line
RDC,line+LDC,line
+
+ ACCB
RAC,line+LAC,line
RAC,line+LAC,line
LS CDC
VS
LS
Vc
CDC
VS
Rfault § 0
Vc
Rfault
-
-
Fig. 4. Current flow during the reclosing process after clearing AC fault.
Fig. 3. Current flow by three-phase short circuit fault in LADS.
2.2. Transient analysis by events in LADS
3. Protective schemes for hybrid AC/DC LV distribution system
In this section, the transient phenomena are analyzed according to events such as the fault occurrence in the AC side, and the opening and reclosing of the ACCB. When a fault occurs in the LADS, the bulk of the fault current tends to flow towards the fault location in general. Thus, the impact on the downstream LDDS is slight with respect to the current. Although an unbalanced voltage could be induced at the input terminal of the AC/ DC converter according to the fault type, a variety of solutions are available to produce a normal output, as proposed in [35–37]. Besides, it gives little influence on the system because the AC power cannot be supplied to LDDS through AC/DC converter by the following operation of ACCB. In a three-phase short-circuit fault, however, the power supply to the LDDC is instantaneously prevented because the source current rarely flows downstream of the fault location. Furthermore, the semiconductor switches are deliberately opened due to the discharge current of Vc flowing toward the fault location via the semiconductor switches as shown in Fig. 3. The current flows along the series RLC circuit such that it can be expressed in an equation similar to (1). Only the values of R, L, and C are decided by the corresponding path. The ACCB is tripped according to the time-current curve after an AC fault occurs. Once the ACCB is opened, the LDDS cannot be supplied, except by the DG interconnected with the LDDS. Therefore, similar to the three-phase short-circuit fault, the LDDS could not be supplied. Moreover, the CDC discharge could result in the deliberate opening of the semiconductor switches in the same manner as in Fig. 3. Nevertheless, the current by CDC discharge flows toward the load side if the semiconductor switches have already been opened before the ACCB opens. From the result of the transient analysis above, it is evident that the process from the AC fault occurrence to the opening of the ACCB could cause the deliberate opening of the semiconductor switches in the AC/DC converter. Finally, in the LADS, the ACCB reclosing scheme is performed to identify whether the fault is temporary. During the reclosing process, an inrush current flows in the LADS whenever the ACCB recloses. In an AC temporary fault, as shown in Fig. 4, this inrush current flows completely into the AC/DC converter and could damage the anti-parallel diodes. Thus, a hybrid AC/DC LV distribution system cannot operate normally although the fault is identified as temporary. However, in a permanent fault, the anti-parallel diodes are not damaged by the inrush current because the inrush current flows along the fault path. However, the ACCB is locked out such that the whole hybrid AC/DC LV distribution system experiences power outage. Moreover, the LDDS cannot be operated normally even though the DG is interconnected with the LDDS. This is because an abnormal loop path due to the AC fault still exists and the LDDS is not isolated from the LADS. In conclusion, the LADS should be kept isolated from the AC/DC converter during the reclosing process and after the fault is identified as permanent.
This section first proposes the protection schemes for each distribution system by introducing an additional solid state circuit breaker (CBIT) before the AC/DC converter. This CBIT is introduced with two main purposes: (1) a backup protection for a DC fault in the case the DCCB is malfunctioned, (2) a protection of VSC and LDDS from AC fault and the operation of ACCB, other than resumption of LADS. Subsequently, the coordination for two proposed protection schemes is developed to prevent the proposed protection schemes from causing malfunction to each other. 3.1. Protection scheme for LDDS The protection scheme for the LDDS is proposed to improve the reliability by interrupting the DC fault rapidly. This scheme consists of the main protection with DCCB and a backup protection with CBIT; their schematic diagrams are shown in Fig. 5. The main protection protects the AC/DC converter as well as the LADS against a DC fault. Thus, the DCCB must interrupt the DC fault before tC to prevent the inflow of IL and IS. As the detection factor for the main protection, in this study, the current derivative (diDC/dt) is used because iDC dramatically increases within a few microseconds after a DC fault occurs. This factor can response under initial condition of the capacitive discharge current [38]. Moreover, this method can prevent the ACCB from malfunctioning because the required interruption time (tACCB) in the LADS is generally much longer than the corresponding time (tDCCB) in the LDDS. The following equations, (4) and (5), show the criterion to detect a DC fault and the relation among each time point, respectively. In (4), diset/dt is the setting value, determined to satisfy (5) in the given system conditions. (4)
diDC / dt > diset / dt Satisfied
IS
LADS iIT
CBIT Block
Unsatisfied
Vc
~ =
DCCB
= diDC/dt
=
DC load
=
DC load
Trip
(a) Main protection Trip
IS
CBIT
LADS iIT
Satisfied
Vc
~ =
DCCB IL
Failure
diDC/dt
=
Trip
(b) Backup protection Fig. 5. Schematic diagram of protection scheme for LDDS. 523
Electrical Power and Energy Systems 105 (2019) 521–528
C.-H. Noh et al.
Utility
(5)
tDCCB < tC ≪ tACCB
ACCB
For the backup protection, CBIT operates when the DCCB fails. As the detection factor, Vc is used because the rate of change of Vc is relatively less than that of iDC [39]. The criterion for detecting a DC fault is expressed by
Intertrip iAC
(6)
VC < Vset
This section proposes the protection scheme for the LADS. In this scheme, the main purpose is to isolate the LADS from the downstream of the hybrid AC/DC LV distribution system. For the AC/DC converter, the inflow of inrush current due to the ACCB reclosing scheme can be blocked through this scheme. In addition, from the LDDS perspective, the protection scheme could enable the DC loads to be soundly supplied by the DGs even though an AC fault occurs or the ACCB is opened. This type of protection scheme is realized by an intertripping scheme between the ACCB and CBIT as shown in Fig. 7. The intertripping scheme is the controlled tripping of a circuit breaker to complete the circuit isolation of a piece of apparatus in sympathy with the tripping of another circuit breaker [40]. In the basic intertripping scheme, the signal is transferred to the corresponding circuit breaker when a circuit breaker is tripped. In this study, a permissive intertripping method is used, in which whether the specific condition is satisfied is checked before the corresponding circuit breaker is tripped. This scheme generally takes approximately 1.5 ms in the distribution system [40]. The time is defined as tinter. When an AC fault occurs, the ACCB is tripped by the overcurrent relay according to the conventional time-current curve. Once the ACCB opens, the signal from the sending end (ACCB) is transferred to the receiving end (CBIT), which triggers the permissive intertripping scheme. To trip CBIT, the given specific criterion is checked whether it satisfies
In this protection scheme, CBIT must not operate when the DCCB interrupts the DC fault within tDCCB. However, Vc decreases gradually despite the timely operation of the DCCB, which results in the malfunction of CBIT. In this regard, additional criterion is applied to the backup protection besides (6), which is based on the current characteristic in the LADS under a DC fault. The CBIT therefore works with the assumption that the main protection fails, if both (6) and (8) are met simultaneously. (8)
Here, iIT is the RMS value of the current at the input terminal of the AC/DC converter. As the setting value for backup protection, iblock is set to be higher than the rated current in the LDDS. Finally, Fig. 6 illustrates the transient phenomena for the detection factors during the process from fault occurrence to the operation of the protection scheme. In Fig. 6, iset means the setting value for the ACCB. In addition, tdelay(#) is marked in the figure, which represents the time physically required to open a circuit breaker. Specifically, the sign, “*” means the delayed time by the inverse-time relay in the LADS. When a DC fault occurs, both iDC and iIT increase and Vc decreases. Thus, the DCCB can be opened according to (4) as the main protection (black solid line) and other criteria don’t affect to the protection system of LDDS. On the other hand, in case the DCCB cannot work (blue mixed – solid and double dotted – line), CBIT works as the backup protection according to the criteria (6) and (8) in the second and third graph.
Main protection
Fault Occurrence
iAC < iset − o
DCCB open diset/dt
iset − o < iAC < iset − c
tdelay(1) tDCCB
tCBIT
Vset tdelay(2) t0
tDCCB
tCBIT
tACCB iset
iIT
tdelay(3)*
iblock
Backup protection Fault Occurrence
DCCB failure
(10)
where iset_c is the setting value for reclosing CBIT, which is determined to be higher than the rating value in the LADS. Since iAC is measured at the input terminal of the LADS and CBIT is still opened, the setting value (iset_c) is decided based on the rating current for the AC loads. The delayed time is the same as that by opening the CBIT. If CBIT is reclosed following the ACCB, the starting current due to the AC/DC converter appears and could malfunction the protective devices in the hybrid AC/ DC LV distribution systems. Thus, in the proposed protection scheme, this starting current is ignored by introducing the dead time (tdead) after CBIT recloses. A series of the processes for the proposed scheme result in the change in iAC, as illustrated in Fig. 8 except the impact by the starting current. Additionally, the intertripping signal is included in Fig. 8. The expression of states (open and reclose) and time (t0–t4) in Fig. 8 are associated with the ACCB. When a AC fault occurs, iAC increases and the ACCB can be opened according to the specific time-current curve. Once ACCB works, the CBIT is intertripped according to (9). While conducting a reclosing scheme of ACCB, the CBIT is lock-out or closed according to
tACCB
Vc
(9)
where iset_o is the setting value for intertripping CBIT, which can be set to be much lower because the current does not flow after the ACCB is opened. In addition, some delay occurs in the process, which includes tinter and the time (trms) to calculate the RMS value of the AC current (iAC). Next, the sending end (ACCB) sends the signal continuously to inform that the ACCB state is changed during the reclosing of the ACCB. Once CBIT is opened by (9), CBIT is not closed until an AC fault is identified as temporary. That is, CBIT keeps open. The criterion where CBIT is reclosed is expressed by
diDC/dt
t0
Communication link
LDDS
Operation Criteria
3.2. Protection scheme for LADS
(7)
iIT > iblock
AC load
~ =
Fig. 7. Schematic diagram of protection scheme for LADS.
where Vset is the setting value. Vset is decided based on the required interruption time (tCBIT) of CBIT. To decide tCBIT, two important conditions should be considered. First, the primary purpose of CBIT is to prevent the ACCB from malfunctioning. The other is that CBIT must operate after the DCCB as a backup protection. That is, in the given system circumstances, Vset should be determined to satisfy (7).
tDCCB < tCBIT < tACCB
CBIT
CBIT open
Fig. 6. Detecting factor waveforms according to the protection scheme in LDDS. 524
Electrical Power and Energy Systems 105 (2019) 521–528
C.-H. Noh et al.
ACCB operation
Open p
Reclose
Fault Occurrence
Temporary Fault
Open p
Reclose
Open p
Table 2 States according to sequence of LDDS protection scheme.
Reclosing Fault Clearance
t0
State
t3
t2
t1
iset_c
iAC
S1 S7
iset_o Permanent Fault
t0
t1
t2
t3 Reclosing
t4
t0
t1
t2
t3
t4
Fault Occurrence
ACCB
Signal
Sequence of LDDS protection scheme
t4
SACCB
SIT(AC)
SIT(DC)
1 1
1 1
1 0
Normal state Backup protection: Must be ‘0’
S1 (111)
Open of ACCB / 1
Charge of CDC / 1
Transfer the signal & Check the condition for intertriping CBIT
CBIT
t0+trms+tinter
S2 (011)
t3+trms+tinter Standby(Open) Standby(Open)+Lockout
Fig. 8. Waveform of iAC and intertripping signal according to the protection scheme in LADS.
S3 (001)
(10). In the case of temporary fault (black solid line) in Fig. 8, rated iAC flows through the operation of ACCB and CBIT in order. On the other hand, in the case of permanent fault (blue mixed – solid and double dotted – line), the CBIT is lock-out.
S7 (110)
Discharge of CDC / 1
Intertrip CBIT / 0
CBIT operation
Discharge of CDC / 0
S4 (010) Intertrip CBIT / 0
Discharge of CDC / 0
Reopen of ACCB / 0
S5 (000)
Reclose of CBIT / 1
S6 (100)
Reclose of ACCB / 0
Completion of reclosing scheme / 0
Lock out
3.3. Protective coordination for hybrid AC/DC LV distribution system
Fig. 9. State diagram for controlling CBIT in protective coordination for hybrid LV distribution system.
The proposed protection schemes in Section 3.1 and 3.2 typically require the operation of CBIT. Two different signals could be transferred to CBIT such that the method to select the correct signal is necessary. For this purpose, three possible cases are preferentially discussed. The first case is when CBIT opens as a backup protection against a DC fault. When the DCCB fails to interrupt a DC fault current, the trip signal (SIT(DC) = 0) is transferred to CBIT. However, from the LADS perspective, the trip signal (SIT(AC) = 0) for CBIT cannot be transferred because the ACCB is still kept closed. That is, the signals for CBIT do not coincide with each other. Another case is the inconsistency of trip signals for CBIT at the fault interruption juncture. Once an AC fault occurs, CBIT is opened following the ACCB. Although both SIT(DC) and SIT(AC) with zero values are transferred to CBIT, the time delay could appear between them. Finally, when CBIT is reclosed after an AC fault is identified as temporary, the signal (SIT(AC) = 1) to reclose CBIT is transferred to CBIT through the intertripping scheme. However, the signal (SIT(DC) = 1) to reclose CBIT is not the output because CDC in the AC/DC converter cannot be charged until CBIT recloses. In this case, the inconsistency between two signals occurs as well. As the countermeasure for the inconsistency between the signals from the LADS and LDDS, in this study, the protective coordination to be controlled according to the combination of the signals (SACCB) for the ACCB, SIT(AC), and SIT(DC) is proposed. First, it presents the actual signal values according to the sequence of the proposed protection schemes through Tables 1 and 2. The values 1 and 0 in the two tables represent
the block signal and trip one, respectively. As shown in two tables, the combination of three signals (SACCB, SIT(AC), SIT(DC)) informs which value should be output and transferred to CBIT when SIT(AC) and SIT(DC) are inconsistent with each other. Although different values are required in the two protection schemes, in state S7, a clearly distinguished state transition is found: S6 to S7 in the LVAC protection scheme and S1 to S7 in the LVDC. Thus, the two proposed protection schemes can be coordinated through the logic expressed by the mealy state diagram in Fig. 9. For reference, it is marked “j/k” during each state transition, which denotes the event/output (sigCBIT). In Fig. 9, the state transition from S1 to S7 via other states describes the LVAC protection scheme. It includes two different state transitions from S2 to S5 because it cannot estimate the time that satisfies the corresponding criteria according to the fault conditions. In addition, the state transition from S5 to S6 and reverse are repeated until the reclosing scheme is completed or an AC fault is identified as temporary. If the reclosing scheme is completed, two protective devices (ACCB and CBIT) are locked out. Otherwise, the state is transited to S6 via S7. Nevertheless, a direct state transition from S1 to S7 illustrates the LVDC backup protection scheme. 4. Simulation and verification 4.1. Test system and simulation conditions
Table 1 States according to the sequence of LADS protection scheme. State
S1 S2 S3 S4 S5 S6 S7
Signal
In this section, a test hybrid AC/DC LV distribution system is modeled as the radial type, as shown in Fig. 10. In addition, a photovoltaic (PV) system is included in the LDDS to verify that the proposed protective schemes and their coordination work well even when interconnected to the DG. The detailed data of the test system and the setting values for the protective schemes are summarized in Table 3. The setting values are determined based on the criteria described in Section 3. Additionally, the reclosing scheme is assumed as a 2 fast 2 delay operation (2F2D) in this study, and its delayed time is arbitrarily determined to lessen the simulation time. In this study, only four representative cases are presented in the
Sequence of LADS protection scheme
SACCB
SIT(AC)
SIT(DC)
1 0 0 0 0 1 1
1 1 0 1 0 0 1
1 1 1 0 0 0 0
Normal state Open of ACCB by AC fault Intertrips CBIT: Must be ‘0’ Keeps CBIT: Must be ‘1’ Open of CBIT by intertripping scheme Reclose of ACCB Identification of temporary fault: Must be ‘1’
525
Electrical Power and Energy Systems 105 (2019) 521–528
C.-H. Noh et al.
AC grid 1.0
signal
Transformer (22.9/0.38kVAC, 60Hz)
LVAC bus
0.0
2km
1km
S1
ACCB
ACCB
S2 ~ S6
Point A
Fault 1200 occurrence
iAC [A]
AC load
1500
AC load
~
(200kW, 380VAC/1500VDC)
=
200kW
0 1000
Point B
600
800
200
400 -200 0.5
DC load
VC [V]
DCCB
= converter
PV
iAC(a) iAC(b) iAC(c)
2000 iIT(a) iDC 1600 VC 1200
LVDC bus
1km
DC/DC
Re-startup of AC/DC converter
300
DCCB
=
S1
600
iDC & iIT[A]
1km
Fault clearance
S7
900
CBIT
AC/DC converter
sigACCB sigDCCB sigCBIT
ACCB opens & recloses
(MV supply)
1.0
1.5
2.0
0 3.0
2.5
Time [s]
Fig. 10. Test hybrid AC/DC LV distribution system.
Fig. 11. Simulation results in case I. Table 3 Simulation conditions.
0.164 Ω/km 0.26 Ω/km
Load capacity
AC loads DC loads
50 kW for each point 100 kW
AC/DC converter
Ls CDC
1 mH 5000 μF
Photovoltaic system
Output voltage Output power
1500 VDC 50 kW
Setting values for protective schemes
diset/dt Vset iblock iset_o iset_c
30 kA/s 500 V 180 A 50 A 500 A
2F 2D
0.1 s 0.3 s
Delayed time in reclosing scheme
signal
Resistance Reactance
0.0 S2 ~ S6
Lock out
S5
1500
Fault 1200 occurrence
iAC(a) iAC(b) iAC(c)
900 600 300 0 1000 600
800
200
400 -200 0.5
Fault conditions
2000 iIT(a) iDC 1600 VC 1200
VC [V]
Table 4 Simulation cases. #
1.0
S1
iDC & iIT[A]
Distribution line constant
sigACCB sigDCCB sigCBIT
ACCB opens & recloses
Input values
iAC [A]
Parameter
1.0
1.5
Time [s]
2.0
2.5
0 3.0
Fault location
Fault type/duration
Fault resistance
Case I Case II
Point A
Ground fault/Temporary (0.5 s) 3Ф short circuit fault/Permanent
0.1 Ω 0.1 Ω
Fig. 12. Simulation results in case II.
Case III Case IV
Point B
Pole-to-Pole fault/Permanent Pole-to-Pole fault (DCCB failure)/ Permanent
10 Ω 0.1 Ω
resistances ranging from the bolted fault to 10 Ω. The only representative simulation results among them are included herein. 4.2. Simulation results and discussion
various fault conditions, which are arranged in Table 4. The first two cases (cases I and II) are conducted for the AC fault, which are subject to the verification that the proposed protection scheme works well regardless of the fault duration. The other two cases (cases III and IV) are performed for the DC fault, which focus on the main and backup protection against the DC fault. To verify the applicability and generality besides the performance of the proposed protective schemes, additional simulations are performed in terms of various fault types as well as fault
The simulation results are presented in Figs. 11–14. Each figure includes the signal for the circuit breakers (sigACCB, sigDCCB, and sigCBIT), the waveforms of the detection factors (iIT(Ф), diDC/dt, and Vc) and the currents (iDC, iAC(Ф)) in both the LVAC and LDDS as occasional demands. For cases I and II, it is verified that sigACCB and sigCBIT are normally output in the given fault conditions, as shown in Figs. 11 and 12, respectively. Both figures are discussed step by step as follows. 526
Electrical Power and Energy Systems 105 (2019) 521–528
signal
C.-H. Noh et al.
step. (3-1) Finally, CBIT recloses (S1 via S7) or is locked out (Lock out via S5) according to the fault duration by intertripping with the ACCB. For case I, the AC fault is cleared at 1.5 s so that it is identified as a temporary fault through the following reclose of ACCB. And then, the CBIT is also reclosed. In Fig. 11, at this time (at about 2 s), a high starting current is observed after CBIT is reclosed (S1 via S7). In the proposed protective coordination, both the ACCB and CBIT are not tripped during this period because of the specific duration (tdead) that allows the overcurrent during the re-startup of the AC/DC converter. After its completion (at about 2.5 s), it can estimate that the hybrid AC/DC LV distribution system operates normally through the waveforms in the bottom-most figure in Fig. 11. (3-2) On the other hand, a high starting current is not appeared while the ACCB works it reclosing scheme until about 2.5 s. That is because CBIT is locked out as shown in Fig. 12 (Lock out via S5). In conclusion, the power by AC source can’t be supplied to both AC and DC loads. It is validated that the proposed protective schemes and their coordination works well regardless of the fault type through case II in Fig. 12.
sigACCB sigDCCB sigCBIT
1.0 DCCB opens 0.0 S1
400 300
1600 1200 800
200
400
100 0 0.5
1.0
1.5
2.0
Time [s]
2.5
300
Signal = 1
20
200 Signal = 0
100 0 0.990
0.995
1.000
1.005 Time [s]
1.010
10
diDC/dt [kA/s]
Fault occurrence
400
3.0
0
50 iDC diDC/dt 40 sigDCCB sigCBIT 30
500
iDC [A]
2000
iAC(a) iIT(a) VC
Fault occurrence
VC [V]
iAC & iIT[A]
500
Next, for cases III and IV, it is also verified that both sigDCCB and sigCBIT are normally output in the given fault conditions through Figs. 13 and 14. In particular, the bottom-most figures in both figures include the waveform for the magnified range because the capacitive discharge current lasts for only a few milliseconds. Both cases correspond to the LDDS protection scheme under the DC fault, which are discussed in detail as follows. According to the well-controlled signals, in case III of Fig. 13, the DCCB opens immediately after a DC fault occurs (S1). Thus, the capacitive discharge current (iDC) in the third plot is interrupted within 1 ms after a DC fault occurs. Additionally, due to the rapid operation of DCCB, the voltage across a dc-link capacitor (VC) in the second plot decreases slowly. However, in Fig. 14, the CBIT opens as a backup protection when DCCB fails (S1 → S7). The state transition from S7 to S1 does not appear since the permanent fault is only represented herein. Since the CBIT operates at about 7 ms after a DC fault occurs, for case IV of Fig. 14, the VC in the second plot is fully discharged. The time difference between the main protection and backup protection can be observed. For both cases (case III and IV), it is confirmed the LADS can be normally operated through two figures (Figs. 13 and 14) even if the DC loads cannot be supplied by AC source. In addition, case III validates that the proposed protective schemes and their coordination are effective for a wide range of fault resistance. In conclusion, the proposed protection schemes can not only protect the distribution systems against their internal faults, but also prevents a distribution system from an instantaneous discontinuity of supply by fault occurrence or the operation of protective devices in the other distribution system when applying the proposed protective coordination to the hybrid AC/DC LV distribution system. That is, the reliability of the hybrid AC/DC LV distribution system can be improved by decreasing the power outage area.
0 1.020
1.015
Fig. 13. Simulation results in case III.
sigACCB sigDCCB sigCBIT
signal
CBIT opens 1.0 0.0 S1
S7
500 iAC & iIT[A]
300
1600 1200
200
800
100
400
0 0.5 3000
1.0
1.5
Time [s]
2.0
300 iDC diDC/dt 250 sigDCCB 200 sigCBIT 150
Fault occurrence
2000
Signal = 1
1500
0 3.0
2.5
1000
100 Signal = 0
500 0 0.990
0.995
1.000
1.005 Time [s]
1.010
diDC/dt [kA/s]
2500 iDC [A]
2000
VC [V]
iAC(a) iIT(a) VC
Fault occurrence
400
50 1.015
0 1.020
Fig. 14. Simulation results in case IV.
(1) Both cases correspond to the LADS protection scheme under the AC fault. When the ACCB opens because of the AC fault (S1 → S2), CBIT opens as well after a delayed time (S2–S5). During this period (from 1 s to 1.1 s), the AC rms values (iAC(Ф), iIT(Ф)) in second/third plot increase. (2) Subsequently, the CBIT is kept open while the ACCB is conducting the reclosing scheme (S5 ↔ S6). While the ACCB is repeating ON/OFF (from 1.1 s to 1.5 s), all the measured detection factors (iIT(Ф), diDC/dt, and Vc) in third plot keep the value of zero. On the other hand, the AC rms values (iAC(Ф)) in second plot shows the change of magnitude according to the operation of the ACCB. In the both cases, the simulation results equal to each other until this
5. Conclusions This paper proposes the protective schemes in a hybrid AC/DC LV distribution system and verifies its performance using EMTP. To this end, the transient analysis for events in both the LVAC and LVDC distribution system is first conducted such as in the fault occurrence and protective devices. Based on the analysis results, it is conclude that the events in one distribution system can affect the other system as well as the corresponding distribution system. The mutual effects will disturb the normal power supply to customers and further damage the hybrid AC/DC distribution system. In particular, the AC/DC converter, which plays an important role as the interface between both distribution 527
Electrical Power and Energy Systems 105 (2019) 521–528
C.-H. Noh et al.
systems, could be easily damaged by the overcurrent. Thus, in this study, the protection schemes for each distribution system are preferentially developed, and subsequently coordinated based on the state diagram with a set of signals transferred to the protective device (CBIT). In this regard, the difference in state transition must be distinguished according to the mechanism of each protection scheme. This work achieves not only the protection of each distribution system, but also assures the normal operation even under fault conditions of other distribution system. Especially, the protective weak point of the existing protection schemes for DC distribution system, which cannot protect some transient phenomena due to the events in LVAC distribution system, can be solved in this study as well. Finally, it is concluded that the proposed protective schemes are effective in hybrid AC/DC LV distribution systems as indicated by the simulation results using the EMTP. The simulation results provide the theoretical validity for the proposed research results, but it could be further requested to check the applicability to the practical system. Thus, it will be planned to conduct the experimental measurements in the near future.
[16]
[17]
[18]
[19]
[20]
[21] [22] [23]
Acknowledgment [24]
This work was supported by “Human Resources Program in Energy Technology” of the Korea Institute of Energy Technology Evaluation and Planning (KETEP), granted financial resource from the Ministry of Trade, Industry & Energy, Republic of Korea (No. 20184030202190) and by the National Research Foundation of Korea (NRF) grant funded by the Korea government (MSIP) (No. 2015R1A2A1A10052459).
[25]
[26]
[27]
References [28]
[1] Emhemed Abdullah AS, Fong Kenny, Fletcher Steven, Burt Graeme M. Validation of fast and selective protection scheme. IEEE Trans Power Deliv 2017;32(3):1432–40. [2] Tseng KJ, Luo Guomin. Power electronic-based protection for direct-current power distribution in micro-grids. In: Proc the 2014 international power electronics conference, Hiroshima, Japan; 2014. p. 2145–51. [3] Park Jae-Do, Candelaria Jared. Fault detection and isolation in low-voltage DC-bus microgrid system. IEEE Trans Power Deliv 2017;28(2):779–87. [4] Fletcher Steven DA, Norman Patrick J, Fong Kenny, Galloway Stuart J, Burt Graeme M. High-speed differential protection for smart DC distribution systems. IEEE Trans Smart Grid 2014;5(5):2610–7. [5] Bui Duong Minh, Chen Shi-Lin, Wu Chi-Hua, Lien Keng-Yu, Huang Chen-Ho, Jen Kuo-Kuang. Review on protection coordination strategies and development of an effective protection coordination. In: Proc IEEE PES Asia-Pacific power and energy engineering conference, Hong Kong, China; 2014. p. 1–10. [6] Vanteddu Sri Raju Bushanam, Mohamed Ahmed, Mohammed Osama. Protection design and coordination of DC distributed power systems architectures. Proc. IEEE power and energy society general meeting. BC, Canada: Vancouver; 2013. p. 1–5. [7] Xue Shimin, Chen Chaochao, Jin Yi, Li Yongli, Li Botong, Wang Ying. Protection for DC distribution system with distributed generator. J Appl Math 2014;2014:1–12. [8] Emhemed Abdullah AS, Burt Graeme M. An advanced protection scheme for enabling an LVDC last mile distribution network. IEEE Trans Smart Grid 2014;5(5):2602–9. [9] Park Jae-Do, Candelaria Jared, Ma Liuyan, Dunn Kyle. DC ring-bus microgrid fault protection and identification of fault location. IEEE Trans Power Deliv 2013;28(4):2574–84. [10] Saleh Khaled A, Hooshyar Ali, El-Saadany Ehab F. Hybrid passive-overcurrent relay for detection of faults in low-voltage DC grids. IEEE Trans Smart Grid May. 2017.;8(3):1129–38. [11] Xue Shimin, Gao Feng, Sun Wenpeng, Li Botong. Protection principle for a DC distribution system with a resistive superconductive fault current limiter. Energies 2015;8(6):4839–52. [12] Jin Jian-Xun, Chen Xiao-Yuan. Cooperative operation of superconducting faultcurrent-limiting cable and SMES system for grounding fault protection in a LVDC network. IEEE Trans Ind Appl 2015;51(6):5410–4. [13] Hosseinzadeh Mehdi, Salmasi Farzad Rajaei. Robust optimal power management system for a hybrid AC/DC micro-grid. IEEE Trans Sustain Energy 2015;6(3):675–87. [14] Jianfang Xiao, Peng Wang, Setyawan Leonardy, Chi Jin, Hoong Choo Fook. Energy management system for control of hybrid AC/DC microgrids. In: Proc. IEEE conf. on industrial electronics and applications, Auckland, New Zealand; 2015. p. 778–83. [15] Eajal AA, Abdelwahed Mohamed A, El-Saadany EF, Ponnambalam Kumaraswamy.
[29]
[30] [31]
[32]
[33]
[34]
[35]
[36]
[37]
[38]
[39]
[40]
528
A unified approach to the power flow analysis of AC/DC hybrid microgrids. IEEE Trans Sustain Energy 2016;7(3):1145–58. Qachchachi Nabil, Mahmoudi Hassane, El Hasnaoui Abdennebi. Smart hybrid AC/ DC microgrid: power management based petri nets. In: Proc international conference on information technology for organizations development, Fex, Morocco; 2016. p. 1–6. Eajal AA, El-Saadany EF, Ponnambalam K. Optimal power flow for converterdominated AC/DC hybrid microgrids. In: Proc IEEE international conference on industrial technology, Toronto, ON, Canada; 2017. p. 1–6. Eajal AA, Abdelwahed Mohamed A, El-Saadany EF, Ponnambalam K. Power flow analysis of AC/DC hybrid microgrids. In: Proc IEEE electrical power and energy conference, Ottawa, ON, Canada; 2016. p. 1–6. Rahman Md Shamiur, Hossain MJ, Lu Junwei. Utilization of parked EV-ESS for power management in a grid-tied hybrid AC/DC microgrid. In: Proc. Australasian universities power engineering conference, Wollongong, Australia; 2015. p. 1–6. Hosseinzadeh Mehdi, Salmasi Farzad Rajaei. Power management of an isolated hybrid AC/DC micro-grid with fuzzy control of battery banks. IET Renew Power Gener 2015;9(5):484–93. Nejabatkhah Farzam, Li Yun Wei. Overview of power management strategies of hybrid AC/DC microgrid. IEEE Trans Power Electron 2015;30(12):7072–89. Khederzadeh Mojtaba, Sadeghi Meisam. Virtual active power filter: a notable feature for hybrid ac/dc microgrids. IET Gener Transm Distrib 2016;10(14):3539–46. Sun Kai, Wang Xiaosheng, Li YunWei, Nejabatkhah Farzam, Mei Yang, Xiaonan Lu. Parallel operation of bidirectional interfacing converters in a hybrid AC/DC microgrid under unbalanced grid voltage conditions. IEEE Trans Power Electron 2017;32(3):1872–84. Malik Sarmad Majeed, Ai Xin, Sun Yingyun, Zhengqi Chen, Shupeng Zhou. Voltage and frequency control strategies of hybrid AC/DC microgrid: a review. IET Gener Transm Distrib 2017;11(2):303–13. Xiao Huagen, Luo An, Shuai Zhikang, Jin Guobin, Huang Yuan. An improved control method for multiple bidirectional power converters in hybrid AC/DC microgrid. IEEE Trans Smart Grid 2016;7(1):340–7. Peyghami Saeed, Mokhtari Hossein, Blaabjerg Frede. Autonomous operation of a hybrid AC/DC microgrid with multiple interlinking converters. IEEE Trans Smart Grid 10.1109/TSG.2017.2713941. Dheer Dharmendra Kumar, Doolla Suryanarayana, Rathore Akshay K. Small signal modeling and stability analysis of a droop based hybrid AC/DC microgrid. In: Proc annual conference of the IEEE industrial electronics society, Florence, Italy; 2016. p. 1–6. Alam Farooq, Ashfaq M, Zaidi Syed Sajjad, Memon Attaullah Y. Robust droop control design for a hybrid AC/DC microgrid. In: Proc international conference on control, Belfast, UK; 2016. p. 1–6. Hernandez Jesus Casa, Sutil Francisco Sanchez, Vidal Pedro Gomez. Protection of a multiterminal DC compact node feeding electric vehicles on electric railway systems, secondary distribution networks, and PV systems. Turk J Electr Eng Comput Sci 2016;24:3123–43. Salomonsson Daniel, Soder Lennart, Sannino Ambra. Protection of low-voltage DC microgrids. IEEE Trans Power Deliv 2009;24(3):1045–53. Yang Jin, Fletcher John Edward, O’Reilly John. Multiterminal DC wind farm collection grid internal fault analysis and protection design. IEEE Trans Power Deliv 2010;25(4):2308–18. Baran Mesut E, Mahajan Nikhil R. Overcurrent protection on voltage-source-converter-based multiterminal DC distribution systems. IEEE Trans Power Deliv 2007;22(1):406–12. Nuutinen Pasi, Peltoniemi Pasi, Silventoinen Pertti. Short-circuit protection in a converter-fed low-voltage distribution network. IEEE Trans Power Electr 2010;28(4):1587–97. Yang Jin, Fletcher John E, O’Reilly John. Short-circuit and ground fault analyses and location in VSC-based DC network cables. IEEE Trans Ind Electron 2012;59(10):3827–37. Grotzbach Manfred, Bauta Michael. Modeling of AC/DC converters under unbalanced voltage supply using complex switching functions. In: Proc international conference on harmonics and quality of power, Rio de Janeiro, Brazil; 2002. p. 710–5. Guo Wenjiao, Ren Chunguang, Han Xiaoqing, Wang Peng. The control method of bidirectional AC/DC converter with unbalanced voltage in hybrid micro-grid. In: Proc conference on industrial electronics and applications, Auckland, New Zealand; 2015. p. 381–6. Merzouk Imad, Bendaas Mohamed Lokmane. Improved direct power control for 3level AC/DC converter under unbalanced and/or distorted voltage source conditions. Turk J Electr Eng Comput Sci 2016;24(3):1847–62. Fletcher Steven DA, Norman Patrick J, Galloway Stuart J, Crolla Paul, Burt Graeme M. Optimizing the roles of unit and non-unit protection methods within DC microgrids. IEEE Trans Smart Grid 2012;3(4):2079–87. Gwon GH, Noh CH, Han J, Song JI, Oh YS, Khan MO, et al. A study on protective coordination for low voltage DC last mile distribution system. In: Presented at international conference on power systems transients; 2017. [Online]. Available: < http://www.ipstconf.org/Proc_IPST2017.php > . Protection: signalling and intertripping. In: Network protection & automation guide, 5th ed. Stafford, UK: Alstom Grid; 2011. p. 113–6.