International Journal of Transportation Science and Technology 5 (2016) 17–27
Contents lists available at ScienceDirect
International Journal of Transportation Science and Technology journal homepage: www.elsevier.com/locate/nucengdes
Optimizing scheduling of long-term highway work zone projects Linfeng Gong a, Wei Fan b,⇑ a Department of Civil and Environmental Engineering, The University of North Carolina at Charlotte, EPIC Building, Room 3366, 9201 University City Boulevard, Charlotte, NC 28223, United States b Department of Civil and Environmental Engineering, The University of North Carolina at Charlotte, EPIC Building, Room 3261, 9201 University City Boulevard, Charlotte, NC 28223, United States
a r t i c l e
i n f o
Article history: Received 23 December 2015 Received in revised form 17 March 2016 Accepted 17 May 2016 Available online 16 June 2016 Keywords: Work zone Scheduling Optimization Genetic algorithm User equilibrium
a b s t r a c t The impacts of work zone activities can be summarized into the following types: safety impact (on both motorists and workers), mobility impact, economic considerations, environmental concerns, user cost as well as contractor’s maintenance cost. Various interest subjects may focus on different aspects of the six areas identified above. In this study, the impacts of scheduling long-term work zone activities are analyzed from the perspective of traffic agencies and jurisdictions. A bi-level genetic algorithm (GA)-based optimization model is formulated to determine the optimal starting date of each work zone project. The upper-level subprogram minimizes the total travel time over the entire planning horizon, while the lower-level subprogram is a user equilibrium (UE) problem where all users try to find the route that minimizes their own travel time. The demand, and the number of work zones as well as their durations are assumed to be fixed and given a priori. The proposed GA model is applied to the Sioux Falls network, which has 76 links and 24 origin–destination (O–D) pairs. The results of the numerical example indicate that the proposed model can effectively identify the near-optimal solution of the long-term work zone scheduling problem. Ó 2016 Tongji University and Tongji University Press. Publishing Services by Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/ licenses/by-nc-nd/4.0/).
1. Introduction With the increasing travel demand and an aging transportation infrastructure system, work zone planning and management have become increasingly challenging because of the significant disruptions of the roadway construction activities caused to normal traffic flow patterns. Many transportation agencies have devoted much attention to scheduling various types of roadway maintenance and rehabilitation (M&R) activities, such as pothole patching, crack sealing, pavement marking, resurfacing, etc. (Weng and Meng, 2013). Various aspects related to planning, designing and execution of road construction works need to be considered in order to minimize the potential detrimental impact on local drivers and, meanwhile, maximize the safety levels for construction workers. As FHWA discussed and synthesized in its two publications, Developing and Implementing Transportation Management Plans for Work Zones and Work Zone Impact Assessment: An Approach to Assess and Manage Work Zone Safety and Mobility Impacts of ⇑ Corresponding author. E-mail addresses:
[email protected] (L. Gong),
[email protected] (W. Fan). Peer review under responsibility of Tongji University and Tongji University Press. http://dx.doi.org/10.1016/j.ijtst.2016.06.003 2046-0430/Ó 2016 Tongji University and Tongji University Press. Publishing Services by Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
18
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
Road Projects, the impacts of work zone activities could be classified into the six groups: safety impact (on both motorists and workers), mobility impact, economic considerations, environmental concerns, user cost as well as contractor’s maintenance cost (Jeannotte and Chandra, 2005; Sankar et al., 2006). It is noteworthy that different interest subjects may focus on distinct aspects of the six groups identified above. In particular, contractors are more concerned with the minimization of the total maintenance cost (Meng and Weng, 2013); from the viewpoint of road users, however, they care more about the influence of work zones on their daily trip mobility and travel cost. As to local transportation jurisdictions and agencies, they need to look at the big picture and find out a comprehensive solution to balance distinct aspects of transportation problems induced by work zone activities. For example, traffic delays from all work zones are typically constrained to a certain amount, say 30 min, to control the impacts of work zone activities on travelers, local business and the environment (Dowling et al., 2004). Among all the impacts identified above, an analysis of mobility impact is of utmost importance. This is because, after the full range of mobility impacts are quantitatively assessed, all other aspects associated with work zone activities, such as safety conditions, economic and environmental impacts, can be determined as well (Hardy and Wunderlich, 2008a). It should be pointed out that the denotations of mobility impact are threefold. First of all, at the link level, work zones usually lead to a reduction in roadway capacity and traffic flow speeds on the roadway segment due to one or more travel lanes being closed (Weng and Meng, 2013); vehicle delays on the corresponding segment may increase as well. Secondly, today’s travelers are able to obtain accurate roadway information through various media (e.g., variable message sign, radio and other advanced traveler information systems), and then choose alternative routes to bypass the construction areas. In this case, the impact of work zone activities on a single roadway segment may propagate upstream into adjacent roadway segments, or even the entire network. Therefore, accounting for traffic diversions at the network level is imperative and affects the decision-making procedure of work zone schedules (Tang, 2008b). Lastly, travel demands between certain origin–destination (O–D) pairs could be affected by road construction works as well. For instance, while implementing construction works on an already congested network, transportation jurisdictions may encourage travelers to shift their scheduled travel plans to off-peak hour or share their trips with other commuters to avoid further deterioration of the transportation system (Luten et al., 2004). Traditional deterministic queuing theory (Dudek and Richard, 1982; Schonfeld and Chien, 1999; Jiang, 2001) and shock wave theory (Wirasinghe, 1978; Newell, 1993) are capable of estimating travel delay and queue length on an individual roadway segment where road work exists. Jiang and Adeli (2003) presented a freeway work zone traffic delay and cost optimization model, in which, the optimal combination of work zone length and starting time (represented as time of day in hours) was determined using average hourly traffic data. Meng and Weng (2013) developed an improved deterministic queuing model to estimate work zone traffic delay, taking into account the variation of traffic speeds. However, the impacts of work zones at the network level, such as changes in route choice behaviors and/or travel demands, are beyond the modeling capabilities of traditional deterministic models. Instead, researchers employed regional traffic assignment tools – both static and dynamic traffic assignment models – to resolve this problem. For instance, Pesti et al. (2010) deployed a dynamic traffic assignment (DTA) tool to quantify and evaluate how traffic patterns change in response to various construction scenarios in the El Paso region, Texas. Although DTA models are capable of performing detailed modeling of traffic dynamics of congestion formulation, spillovers, etc., a number of input data and parameter need to be specified prior to model development and calibration. In contrast, static traffic assignment (STA) model typically requires less input data in terms of travel demand and network representation. The widely recognized advantages of STA models include the ability to solve largescale problems, to converge to precise equilibriums and to provide consistent solutions (if a proper algorithm is used with a sufficient number of iterations). Due to these features, they have been widely used by planning agencies and traffic management centers for decades (Chiu et al., 2011). The main purpose of this study is to develop a macroscopic model to assist transportation agencies and jurisdictions in analyzing the regional level impacts of long-term work zone activities and determining the optimal combination of starting dates of several work zone projects during the scheduling decision-making stage (Hardy and Wunderlich, 2008a). To achieve this goal, a bi-level model is developed to quantitatively assess the mobility impact on the entire road network and, further, provide insightful information for higher level analysis. The remainder of this paper is organized as follows. Section 2 describes detailed aspects related to the model formulation, including model assumptions, notations, as well as model constraints. Section 3 presents the genetic algorithm (GA)-based solution framework to the bi-level model, followed by a numerical example in Section 4. Future research recommendations and concluding remarks are given in Section 5. 2. Methodology 2.1. Model assumptions As stated previously, the main objective of this study is to analyze the mobility impact of work zone scheduling on the entire network from the perspective of decision-makers. In order to clearly define the scope of the research problem, the following assumptions are made: (1) The topological information of the roadway network and the O–D matrix are known, the demand between each O–D pair is fixed (i.e., a STA is considered in this study) and the demands are given in the form of standard passenger unit cars;
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
19
(2) The number of work zones is given, and the estimated project duration of each work zone area is also given; (3) Drivers are greedy and they have a perfect knowledge of the roadway network. 2.2. Mathematical notations The network design problem can be described in terms of nodes, links, and routes. To facilitate the process of problem discussion, the following notations are adopted throughout the paper. Consider a connected network with N nodes and L links: -
l = link index, l ¼ 1; 2; . . . ; L; i, j = node index, i; j ¼ 1; 2; . . . ; N; M = the total number of work zones, M 6 L; lm = the corresponding link index of work zone m; lm is a subset of lðm ¼ 1; 2; . . . ; MÞ; P ij = a set of paths between origin i and destination j;
-
f p = the flow on the p-th path between origin i and destination jðp 2 Pij Þ; Cl = the basic capacity of link l; T lm = the estimated maintenance/construction duration of the m-th work zone project (on link); clm = the capacity reduction factor of work zone m (on link lm), 0 6 clm 6 1;
ij
- dijlp = 1 if link l is used in path p which connecting origin i and destination j; otherwise dijlp = 0; -
dij = a priori demand between origin i and destination j; t l ðv l Þ = the travel time on link l given link volume v l , l ¼ 1; 2; . . . ; L; T max = the maximum project deadline for all work zone activities; t lm = the project starting date of the work zone m (on link lm).
2.3. Model formulation Obviously, the starting date of each work zone project will significantly impact network performance. In an extreme case, if all work zone projects commence at the same time, the capacity of the entire road network could be reduced to a very low extent; therefore, the roadway segments may become highly congested. Various combinations of the starting date of each work zone project would lead to distinct capacity supply status of the network. Taking Fig. 1a as an example, this is a simple network consisting of 9 nodes and 24 links. Both links 4 and 21 are the candidate roadways that need to be maintained in the near future ðlm ¼ 4; 21Þ. Assuming that the project durations on both roadway segments are equal (i.e., T4 = T21), and the starting date of both projects are t4 and t21 respectively, as shown in Fig. 1e, in such cases, there will be four status representing different roadway capacity combinations during the entire planning horizon [1, Tmax]: (1) S1 is the basic state of the road network, no road segment is experiencing construction activities (i.e. all roadway segments in the network keep the basic capacity unchanged), as shown in Fig. 1.a. Note that in this case, the network state S1 comprises two periods over the entire planning horizon – [0, t4] and ½t 21 þ T 21 ; T max . (2) During state S2, only link 4 is maintained, as shown in Fig. 1.b. The capacity of link 4 reduces from C4 to c4 C 4 (0 6 c4 6 1) and it lasts from t4 to t21. (3) Both links 4 and 21 are maintained during state S3, as shown in Fig. 1.c. The capacity of links 4 and 21 decreases from C4 and C21 to c4 C 4 and c21 C 21 (0 6 c4 ; c21 6 1), respectively. This state covers the period from t21 to t 4 þ T 4 . (4) State S4 is similar to state S2, only link 21 is under construction condition, as shown in Fig. 1.d. The capacity of link 21 reduces from C21 to c21 C 21 and it lasts from t4 + T4 to t21 + T21. However, in another scenario (Case 2), the two construction projects begin at the same time, i.e. t4 = t21. As a result, only two status, S1 and S3, exist throughout the whole planning period [1, Tmax], as exhibited in Fig. 2. More generally, if the total number of work zones is M, for each single day between ½1; T max , the number of links that need to be maintained could be 0, 1, 2, , M; which indicates that the total amount of all possible status that the roadway network M may experience equals C 0M þ C 1M þ þ C M M ¼ 2 . As M increases, the elapsed time used for finding out the optimal combination of work zone starting date increases drastically. Thus, developing an effective and accurate solution is of great importance to solve the work zone scheduling problem during the scheduling-decision stage. In this study, a bi-level GA-based optimization framework is proposed to determine the optimal starting date of each project. Basically, the bi-level programing formulation involves two players at different levels: the leader and the follower. The two levels have their own decision variables and objectives, and they make an attempt to optimize their own objectives in sequence (Fan and Gurmu, 2014). In this study, the upper-level subprogram is to minimize the total travel delay (in terms of v eh timeunits) over the entire planning horizon, while the lower-level subprogram is a static user equilibrium UE formulation. The objective function of the upper-level subprogram, which minimizes the total travel delay (TTD), is expressed as follows:
20
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
1
4
1
2
8
11
14
24
19
11
14
18
17
c. Two links (4 and 21) were maintained ( S2
)
24
9 23
d. Only one link (21) was maintained ( S4
17
22
8 21
S3
)
S1 Tmax
4
t4
6
14
19
23
0
13 16
20
10
7
15
5
7
9
S1
5
12
22
8 21
11
9
24
19
3 6
4
6 16
20
7
2
2
8
13
5
10
1
7
)
4
3
15
12
9 23
b. Only one link (4) was maintained ( 3
9
17
22
1
5
24
8
6
4
18
)
2 3
14
21
4
1
6 16
20
10
23
1
13
7
9
a. Basic status of the network (
2
18
17
7
15
5
19
8 21
5
12
22
7
11
4
6 16
20
3 6
9
13
12
8
2
8
7
15
5
10
2 3
5
9
4
1
3 6
4
18
1
2 3
t4+T4 21
t21 t21+T21 e. Starting date scheduling (Case 1) Fig. 1. Various network capacity combinations (Case 1).
2M X L X ds ðt l1 ; tl2 ; . . . ; t lM Þ ½t sl ðv sl Þ t 0l v sl
min
tl ;tl ;...;t l 1
2
M
ð1Þ
s¼1 l¼1
Subject to
1 6 t lm 6 T max T lm ðm ¼ 1; 2; . . . ; MÞ
ð2Þ
2M X ds ðt l1 ; t l2 ; . . . ; t lM Þ ¼ T max
ð3Þ
s¼1
where ds ðtl1 ; t l2 ; . . . ; t lM Þ = the number of days when the network is under status sðs ¼ 1; 2; . . . ; 2M Þ, t 0l = free flow travel time on link lðl ¼ 1; 2; . . . ; LÞ, v sl = the solution for the following lower-level subprogram, which represents the deterministic UE given fixed O–D demand:
min
L Z vl X l¼1
0
C l ðxl Þdx
ð4Þ
21
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
1
4
1
3
3
2
8
11
5
7
2
8
14
5
19
18
17
8
7
)
9 23
b. Two links (4 and 21) were maintained (
S3
0
17
22
21
a. Basic capacity status of the network (
24
8
23
S1
14
19
9
21
16
20
10
22
7
6
12
24
7
15
13
4
16
20
5
9
6
12
3 6
11
13
5
10
2 3
15
9
4
1
6
4
18
1
2
)
S1 Tmax
4
t4+T4
t4 21
t21 t21+T21 c. Starting date scheduling (Case 2) Fig. 2. Various network capacity combinations (Case 2).
Subject to
vl ¼
N X X
ij
f p dijlp ; l ¼ 1; 2; . . . ; L
ð5Þ
i;j¼1p2Pij
X
ij
f p ¼ dij ; i; j ¼ 1; 2; . . . ; N
ð6Þ
f p P 0; p 2 Pij ; i; j ¼ 1; 2; . . . ; N
ð7Þ
p2P w ij
where the expression C l ðxl Þ in the objective function of the lower-level subprogram stands for the generalized link performance function, which is usually expressed by the widely used Bureau of Public Roads (BPR) link performance function:
"
t0l 1 þ a
b #
vl Cl
ð8Þ
where a, b = empirical coefficients. Common values for the coefficients are a = 0.15 and b = 4. It is normally assumed that capacity at this value of a in the preceding formula represents the level of traffic intensity whereby the travel time on the link is 15% higher than the travel time at free flow. 3. Model solution framework The genetic algorithm (GA), as a well-known type of adaptive heuristic algorithm, is inspired by the evolutionary ideas of natural selection and genetics (Holland, 1975; Goldberg, 1989; Michalewicz, 1999). Genetic algorithms have been proven to provide a robust search as well as a near-optimal solution in a reasonable amount of time. The working process of genetic algorithms is simple to understand; it involves nothing more than copying strings or swapping partial strings. The simplicity of the operations and the ability to find good solutions are two characteristics that make this method very suitable for solving network design problems (Fan, 2004; Fan and Machemehl, 2006). Fig. 3 presents a flow chart of the whole GA process for the stated problem.
22
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
Initialization of project starting date for each maintenance-required link
Generation = 0, GA initial solution Lower-level network analysis
Determine all possible network status and the duration for each state
GA objective function evaluation Generation ++ Tournament selection Crossover between solutions
Solution mutation
Maximum Generation? No Yes
Output results Fig. 3. Flow chart of the GA-based solution framework.
4. Numerical example 4.1. Example network description The Sioux Falls network shown in Fig. 4 was selected as a numerical example to illustrate the effectiveness of the proposed methodology. This example network contains 24 travel demand zones, 76 links, and 576 O–D pairs and has been used in many publications (Yin et al., 2015), as it is good for code debugging. Besides, Bar-Gera (2015) found the Sioux Falls user equilibrium solution using the quadratic BPR cost functions, which could be used for cross-checking results. In this study, road construction activities were assumed to be performed on 5 links in the Sioux Falls network (i.e., lm ¼ ½12; 36; 41; 56; 68), represented by red dotted lines in Fig. 4. The construction period on each link was assumed to be T lm ¼ ½90; 180; 270; 360; 450. They account for about 6.5 percent of all links in the Sioux Falls network. It is worth mentioning that, even if the number of links under construction changes (e.g., M increases), the core model structure will remain invariant, as shown in Eqs. (1)–(8). It is also likely that the computing time will remain unchanged even as M increases. However, speeding up the optimization algorithms can still be potentially addressed using some techniques, such as the two-stage hybrid GA methodology proposed by Cheu et al. (2004), Ma et al. (2004). It was further hypothesized that the capacity of the road lm reduced by half due to work zone activities, which means clm ¼ 0:5ðlm ¼ ½12; 36; 41; 56; 68Þ. Note that these parameter values were selected for illustration purposes, when the size of the network and the number of links to be maintained are fixed, the specific value of construction durations and capacity reduction factors will not affect the effectiveness of the proposed methodology. For instance, if link 12 (lm = 12) is fully closed, the only change that needs to be made is to revise c12 to 0. It is well known that parameters inherent in the GA algorithms need to be carefully chosen, as they will have some effects on the optimal solution. For example, when the chosen population size is too small, the algorithm may not be able to get good coverage of the solution space; however, it is also true that a large population size requires longer time for the algorithm to converge. Likewise, a low mutation rate could get the algorithm stuck in local minima, while a high mutation rate could bring risks to the individuals by ‘‘jumping” over a potentially good local optimal solution. In determining the inherent parameters of the GA algorithm, the researchers simultaneously considered the size of solution space of the numerical example and some previous experience in selecting GA parameters (Chen and Yang, 1992; Recker and et al., 2005). In addition, several combinations of the parameter values were tried and their performance was evaluated as well. Finally, the following values were selected in applying the GA to the numerical experimentation: population size, 64; maximum number of generation, 200; crossover probability, 0.7; mutation probability, 0.05. Based on the preceding assumptions, the proposed GA procedure was implemented using MATLAB software package. Detailed results are synthesized and discussed in subsequent sections.
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
23
3 1
2 1
2
5
4 8
11
3
4
5
6
14
15 6
9
12 13
23
16
19
21 7
35
10
31
17
9
8
7
24 25 33
26
22
27
12
47
48
11
18
16 29 51
54
55
10 32
36
20
18 50
49
52
30 34
40
28
17
43 53
41 37
14
38
56
15
71
60
19
44 42
58
57 45 46
67
72 23
59
22
61
70 63 73
76
69
65 68
74 13
66 24
39
62 21
75
20 64
Work zones (assumed) Roadways remain unchanged Fig. 4. Sioux Falls test network data from Bar-Gera (2015).
4.2. Result analysis 4.2.1. Program validation and efficiency analysis In this study, the Frank-Wolfe algorithm was applied to determine link volumes at equilibrium status; at the same time, the Average Excess Cost (AEC) was selected as the convergence criterion of the static UE. The AEC is defined as the total excess cost divided by the total regional flows:
PL AEC ¼
v
P P v l Ni¼1 Nj¼1 jij dij PN PN i¼1 j¼1 dij
l¼1 C l ð l Þ
ð9Þ
where all terms are defined as previously stated except that jij represents the time spent on the fastest path between origin i and destination j. The iteration process of the Frank-Wolfe algorithm terminates when the AEC is smaller than a predefined threshold Tthre (0.5% in this paper).
Link Volume
25000 20000
Best-known link flows solution Calculated
15000 10000 5000 0 1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 Link Number Fig. 5. Comparison of the calculated UE volumes with the best-known solution.
24
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
As presented in Fig. 5, the calculated equilibrium link flows of the experimental network matched very well with the bestknown link flows solution (Bar-Gera, 2015). The maximum, average and minimum differences between the calculated and the best-known link volumes are 45.74 (0.30%), 11.98 (0.11%) and 0.25 (0.003%), respectively. The elapsed times of each sub-program are also recorded during the calculation process. It should be pointed out that the CPU used in this project is an Intel Core i7 (3.40 GHz) eight-core processor. The average elapsed time for the shortest path and Frank Wolfe subprogram is 0.019 s and 9.8 s, respectively. Thus, it can be concluded that the proposed algorithm in this study is able to deal with traffic assignment problems with similar network scales. 4.2.2. Results of the GA-based Bi-level model Fig. 6 provides the average and minimum total travel delay (TTD) obtained from each generation of the GA algorithm. It is quite obvious that, both the average and minimum TTD decreased very quickly during the first 25 generations of the GA; after the 25th generations, the solutions gradually approach to a stable condition with a certain level of variations (which can be explained by the mutation operations in the GA). Fig. 6 indicates that the proposed framework is able to provide an efficient and stable solution to the multiple work zone starting date optimization problem. Since the convergence rate of the GA is associated with the extent of dissimilarities of the chromosomes within each generation, the TTD associated with each network status was carefully examined as well. As illustrated in Table 1, the standard deviation of the TTDs across all 32 network status accounts for 2.54 percent of the average TTD; even the maximum TTD (corresponds with the worst construction scenario) is only 4.77 percent higher than the average TTD. Therefore, one possible reason of the fast convergence of the GA is because of fewer variations of the TTDs among all network status. The other reason that the GA method can find the near optimal solution very quickly is because, the duration of each network status is actually determined by the relative gap between of the starting dates of different construction projects, rather than the absolute starting date of each project within the entire project planning horizon. As delineated in Fig. 7a and b, though the starting date of each work zone area (link 4 and link 21) is different (the starting date for links 4 and 21 are t4 and t21 in Fig. 7a, while the corresponding time in Fig. 7b are t04 and t 021 respectively) each network status has the same duration due to the identical relative gaps in the two scenarios. Therefore, the magnitude of the solution space can be significantly reduced by this property. In addition, the GA compares the performance of a group of chromosomes within each generation, instead of focusing on a single solution only. Such characteristic is able to speed up the process of finding out the near-optimal solution as well. The reason why the discrepancies of the TTDs across various work zone area construction scenarios are not obvious was also examined by the authors. Table 1 exhibited the specific combinations of work zone areas corresponding to each network status as along with the TTD values. As shown in Table 1, if there is only one roadway segment under construction, compared to the other 4 single roadway work zone scenarios, link 41 has the greatest impact on the network performance (status 4). Similarly, the combinations of work zone areas [41, 56], [41, 56, 68], [36, 41, 56, 68], [12, 36, 41, 56, 68] have the biggest impact on the TTD within each sub-category. In order to get a deep understanding of how work zone areas impact the traffic flow over the entire network, network status 4, 26, 32 are selected for further analysis. Meanwhile, the extent of changes in volumes (compared with the base scenario S1 in which no work zone exists) were divided into 5 categories: (1) the percentage of volume increased by greater than 15 percent, denoted by those crimson arrows in Fig. 8; (2) the percentage of link volume increased by 2.5–15 percent, denoted by light red arrows; (3) the changes of volume lies between 2.5 and 2.5 percent, denoted by black arrows; (4) the percentage of volume reductions exist between 15 and 2.5 percent (denoted as light green arrows); and (5) the percentage of volume reductions is greater than 15 percent (represented by thick green arrows). As depicted in Fig. 8a, compared with the base scenario, when there’s only one work zone existing in link 41, none of the roads in the network experienced an increase in volume greater than 15 percent, even though the capacity of link 41 reduced by a half. That is because, under the third assumption in which drivers are greedy and have a perfect knowledge of the network, traffic flows will shift from link 41 to adjacent links, such as links 40 and 42. In this case (S4), the TTD over the entire network increased by only 3.94 percent, compared to S1.
TTD (veh*time unit)
4250000 Avg. TTD
4240000 4230000 4220000 4210000 4200000
1
21
41
61
81
101 121 Generation
141
Fig. 6. Results of the GA-based bi-level model.
161
181
25
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27 Table 1 Analysis of the TTD for each network status. Status ID
Combination of maintenance – required roads
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Mean Std. Max.
0 12 0 0 0 0 12 12 12 12 0 0 0 0 0 0 12 12 12 12 12 12 0 0 0 0 12 12 12 12 0 12
0 0 36 0 0 0 36 0 0 0 36 36 36 0 0 0 36 36 36 0 0 0 36 36 36 0 36 36 36 0 36 36
0 0 0 41 0 0 0 41 0 0 41 0 0 41 41 0 41 0 0 41 41 0 41 41 0 41 41 41 0 41 41 41
0 0 0 0 56 0 0 0 56 0 0 56 0 56 0 56 0 56 0 56 0 56 56 0 56 56 56 0 56 56 56 56
0 0 0 0 0 68 0 0 0 68 0 0 68 0 68 68 0 0 68 0 68 68 0 68 68 68 0 68 68 68 68 68
# of roads maintained
TTD
% change with respect to the uninterrupted network
0 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 5
4,057,889 4,070,675 4,094,175 4,217,866 4,134,090 4,137,361 4,114,822 4,235,606 4,140,933 4,148,835 4,256,679 4,176,535 4,182,133 4,303,348 4,300,228 4,233,446 4,281,680 4,182,280 4,198,352 4,313,127 4,318,597 4,237,501 4,340,911 4,343,189 4,273,262 4,400,493 4,353,428 4,363,083 4,282,760 4,415,440 4,437,326 4,452,763 4,249,963 108,088 4,452,763
0 0.32 0.89 3.94 1.88 1.96 1.40 4.38 2.05 2.24 4.90 2.92 3.06 6.05 5.97 4.33 5.51 3.07 3.46 6.29 6.42 4.43 6.97 7.03 5.31 8.44 7.28 7.52 5.54 8.81 9.35 9.73 4.73 2.66 9.73
Relative gap between 2 projects
S0
S1
0
Relative gap between 2 projects
S2
S3
S0
S0
Tmax
4
t4
t4+T4
S1
0
S2
S0
Tmax
4
t'4
t'4+T4
21
t21
S3
21
t21+T21
t'21
Absolute start time of each project
a. starting date for link 4 and 21 are
t'21+T21
Absolute start time of each project
and
b. starting date for link 4 and 21 are
and
Fig. 7. Differences between the absolute starting dates and the relative gaps of work zone projects.
In Fig. 8b, three work zone areas exist in segments 41, 56 and 68. There are only two roadway segments experiencing an increase in traffic volume greater than 15 percent. Specifically, the increases in links 64 and 73 are 20.6 and 16.1 percent, respectively. Compared to S1, the TTD over the entire network increased by 8.44 percent in this case (S26). Fig. 8c exhibits the worst case in this example, all five work zones are concurrently experiencing roadway construction works. In this scenario, there are seven roadway segments experiencing a volume increase greater than 15 percent. However, the average TTD of the entire network increased by only 9.73 percent, compared with S1. In short, this numerical experimental study not only illustrated that the impact of reducing of the capacity of a single roadway segment can spread over the entire network, but also explained as to (1) why the differences between various network statuses are not obvious, and (2) why the convergence rate of the GA method is fast.
26
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27 3
3
1
2
1
2
1 2
1
5
4 8
11
3
2
6
10
31
23
16
19
25
26
12
10
31
16
47
18
54
8
25 33
16
18
26
11 36
40
28
16 29 51
43
40
46
28
56
19
60
37
14
38 42
71
59
22
61
19
46
67 59
22
61
70 63
63 76
69
65
73
69
21
13
20
75
65 68
74
62
24
76
68
66
39
60
45
23
70
13
56
15 44
67
58
57
72
23
74
52
53
72
73
49
43
58
45
71
18 50
17
41
15 44
42
34
57
14
38
54
30
53
37
18 55
10 32
52 17
41
47
48
30 34
7 20
22
27
12
50 49
19 17
9 24
55
10 29 51
35
20 22
32
23 21
7
7
48
11 36
6 12
13
8
27
5 9
17
9
14
15
4 6
24 33
11
3
12 21
35
4 8
5 9 13
7
5
15
4 6
14
24 39
64
a. Only 1 work zone area (Link 41)
66
62 21
75
20 64
b. 3 work zone areas (Link 41, 56, 68)
3 1
2 1
2
5
4 8
11
3
4
5
6
14
15 6
9
12 13
23
16
19
21 7
35
10
31
17
9
8
7
24 25 33
26
27
12
47
18
48
11
16 29 51
54
55
10 32
36
20 22
18 50
49
52
30 34
40
28
17
43 53
41 37
14
38
56
15
19
44 42
71
58
57
46
67 59
22
61
70 63 76
69
65 68
74 13
66 24
39
Legend X
72 23
73
60
45
62 21
75
20 64
ID of the roads that need to be maintained Percentage of volume increase > 15% Percentage of volume increase 2.5% - 15% Percentage of volume change -2.5% - 2.5% Percentage of volume decrease -2.5% - 15% Percentage of volume decrease < -15%
c. 5 work zone areas (Link 12, 36, 41, 56, 68) Fig. 8. Influence of work zone area on the traffic flow assignment over the entire network.
5. Conclusion and discussion The impacts of the long-term work zone activities on the mobility performance of the entire network were analyzed in this study. A bi-level model was developed to quantitatively investigate the impacts of various combinations of work zone projects. A GA-based heuristic solution method was proposed as well. The results of the numerical example indicated that the proposed GA-based method can be effectively used to determine the near-optimal solutions for the long-term work zone scheduling problem while accounting for the network level impacts of work zone construction activities.
L. Gong, W. Fan / International Journal of Transportation Science and Technology 5 (2016) 17–27
27
As discussed earlier, this research mainly focuses on the influence of work zone areas from the perspective of traffic agencies and jurisdictions. However, from the standpoint of contractors, they may be more concerned with the impacts of work zone schedules on the maintenance cost. Therefore, it is meaningful to build a model to maximize the benefits to both traffic jurisdictions and contractors. Aside from that, even though the proposed method in this study can be applied to deal with work zone scheduling problems during the planning stage, from the viewpoint of traffic management, such model is incapable of describing how traffic flow evolves with time. The potential impacts of work zone activities on traffic demands cannot be analyzed as well. It is important to note that in a previous study, Zhang observed minor reductions in commuting traffic demand due to lane closures on I-5 in Sacramento area. It was concluded that the specific level of demand reduction largely depends on the availability of alternative modes and the extent of public awareness (Zhang, 2011). Last but not the least, accounting for the heterogeneity across commuters is also a meaningful research direction. In this study, we assumed that all drivers are greedy and that they have a perfect knowledge of the roadway network. Although such assumption has been adopted by many researchers for convenience purposes, in reality, however, it is very likely that a large part of the commuters may still prefer to stick to the original route. Herein, in future research, addressing the heterogeneity across drivers, and integrating the dynamic traffic assignment (DTA) as well as incorporating the elastic UE method into the model could improve the accuracy and practicability of the proposed methodology. References Bar-Gera, H., 2015. Transportation test problems.
Accessed Nov. 11, 2015. Chen, A., Yang, C., 1992. Stochastic transportation network design problem with spatial equity constraint. Transportation Research Record: Journal of the Transportation Research Board, No. 1882. Transportation Research Board of the National Academies, Washington, D.C., pp. 14–18. Cheu, R.L., Wang, Y., Fwa, T.F., 2004. Hybrid genetic algorithm-simulation methodology for pavement maintenance scheduling. Comput.-Aided Civ. Infrastruct. Eng. 19, 446–455. Chiu, Y.-C., Bottom, J., Mahut, M., Paz, A., Balakrishna, R., Waller, T., Hicks, J., 2011. Transportation Research Circular E-C153: Dynamic Traffic Assignment: A Primer. TRB, National Research Council, Washington, D.C.. Dowling, R., Skabardonis, A., Alexiadis, V., 2004. Traffic Analysis Toolbox Volume III: Guidelines for Applying Traffic Microsimulation Software, Report No. FHWA-HRT-04-040. FHWA, U.S. Department of Transportation. Dudek, C.L., Richard, S.H., 1982. Traffic capacity through urban freeway work zones in Texas. Transportation research Record: Journal of the Transportation Research Board, No. 869. Transportation Research Board of the National Academies, Washington, D.C., pp. 14–18. Fan, W., 2004. Optimal Transit Route Network Design Problem: Algorithms, Implementations, and Numerical Results Ph.D. dissertation. Univ. of Texas at Austin, Austin, TX. Fan, W., Gurmu, Z., 2014. Combined decision making of congestion pricing and capacity expansion: genetic algorithm approach. J. Transp. Eng. http://dx.doi. org/10.1061/(ASCE)TE.1943-5436. Fan, W., Machemehl, R.B., 2006. Optimal transit route network design problem with variable transit demand: A genetic algorithm approach. J. Transp. Eng. 132 (1), 40–51. http://dx.doi.org/10.1061/(ASCE)0733-947X(2006). Goldberg, D.E., 1989. Genetic Algorithms in Search, Optimization, and Machine Learning. Addison-Wesley, London. Hardy, M., Wunderlich, K., 2008a. Traffic Analysis Tools Volume VIII: Work Zone Analysis – A Guide for Decision-Makers, Report No. FHWA-HOP-08-029. FHWA, U.S. Department of Transportation. Holland, J.H., 1975. Adaptation in Natural and Artificial Systems. University of Michigan Press, Ann Arbor, MI. Jeannotte, K., Chandra, A., 2005. Developing and Implementing Transportation Management Plans for Work Zones, Report No. FHWA-HOP-05-066. FHWA, U.S. Department of Transportation. Jiang, Y. Estimation of Traffic Delay and Vehicle Queues at Freeway Work Zones. In: Presented at the 80th Annual Meeting of the Transportation Research Board, Washington, D.C., 2001. Jiang, X., Adeli, H., 2003. Freeway work zone traffic delay and cost optimization model. J. Transp. Eng. 129 (3), 230–241. Luten, K., Binning, Katherine, Driver, D., Hall, T., Schreffler, E., 2004. Mitigating Traffic Congestion: The Role of Demand-Side Strategies, Publication FHWAHOP-05-001. FHWA, U.S. Department of Transportation. Ma, W., Cheu, R.L., Lee, D.-H., 2004. Scheduling of lane closures using genetic algorithms with traffic assignments and distributed simulations. J. Transp. Eng. 130 (3), 322–329. Meng, Q., Weng, J., 2013. Optimal subwork zone length and project start time for short-term daytime work zones from the contractor’s perspective. Transp. Res. Part C 29, 72–83. Michalewicz, Z., 1999. Genetic Algorithms + Data Structure = Evolution Programs, third ed. Springer, New York. Newell, G.F., 1993. A simplified theory of kinematic waves in highway traffic, Part I: General theory. Transp. Res. Part B 27 (4), 281–287. Pesti, G., Chu, C.-L., Balke, K., Zeng, X., Shelton, J., Chaudhary, N., 2010. Regional Impact of Roadway Construction on Traffic and Border Crossing Operations in the El Paso Region. Center for International Intelligent Transportation Research, Texas Transportation Institute. Recker, W. et al, 2005. Considering Risk-taking Behavior in Travel Time Reliability. Institute of Transportation Studies, Univ. of California, Irvine, CA. Sankar, P., Jeannotte, K., Arch, J.P., Romero, M., Bryden, J.E., 2006. Work Zone Impacts Assessment: An Approach to Assess and Manage Work Zone Safety and Mobility Impacts of Road Projects, Report No. FHWA-HOP-05-068. FHWA, U.S. Department of Transportation. Schonfeld, P., Chien, S., 1999. Optimal work zone lengths for two-lane highways. J. Transp. Eng. 125 (1), 21–29. Tang, Y., 2008b. Optimized Scheduling of Highway Work Zones. New Jersey Institute of Technology. Weng, J., Meng, Q., 2013. Estimating capacity and traffic delay in work zones: An overview. Transp. Res. Part C 35, 34–45. Wirasinghe, S.C., 1978. Determination of traffic delay from shock wave analysis. Transp. Res. 12, 343–348. Yin, K., Wang, W., Wang, X.B., Adams, T.M., 2015. Link travel time inference using entry/exit information of trips on a network. Transp. Res. Part B 80, 303– 321. Zhang, M., 2011. Evaluation of Alternative Construction Plans for I-5 Closure in Downtown Sacramento, Report No. CA11-2072. State of California Department of Transportation.