UK
Offshore
Wind
of a Wind Farm Project - Part 11
Anatomy
G
over
enerating
UK’s
amount
of attention
last
12
months,
of the Kyoto
from renewable
sources by
seen as an important
(MOD)
Even
to its reservations impact
of
blocked
the
will
for
a
example, and the
of electricity
2010 (wind is to this
of Defence
into the debate
regarding
turbines
cerned is the MOD
in the UK
contributor
the Ministry
has entered
the
Protocol 10%
on
So con-
about this, it has even of
a major
wind farm project in Northumberland judicial
due
the negative
radar.
construction
(a
review regarding this farm is now
pending). Table
1: Summary
Following
fair
received
aim to generate
target).
from wind
has
the
because
electricity
power
be
power
procedures
regarding
States
terrorist
atrocities
in
Industry
of America,
however,
it
farm developers
interesting
undergoes
to
see
whether
a significant
wind
shift in polit-
ical perception
as the UK looks to secure
energy
by lessening
on
supply
less
stable
Middle
political
East.
therefore, gy need, wealth
Offshore
one possible especially
such
wind
one considers
oil & gas platform
the UK - an expertise itself
lends
maintenance
to
an
article
for
mandatory
and which
the building
November/December
2001
wind issue,
which
eas-
operating
and operating
: 1.; ‘s
and
farms. Masons
looking
procedures
the Department
RE
the
exper-
construction
Refocus1
consents
building
the
of offshore
In the July/August
are,
to this ener-
ily
Karen the
wrote at
the
regarding
offshore
wind
ofTrade of offshore
and wind
www.re-focus.net
(DTI)
require to fulfil.
Cooksley
of
non-mandatory
in which
these apply.
sents
table
operating The
various
a recap
required
offshore
and
covered
in
and the circumstances
provides
procedures
wind
now consider
procedures
document
The
potential Peter Cassidy”
Masons3
the DTl’s
as the
farms
solution
when
of offshore
its
its dependence
areas,
tise within
farms, of current
the recent
United
wind
on the
con-
for building farms
non-mandatory
in the
and UK.
procedures
are
now described.
Consents Under Section 36 & 37 Electricity Act 1989 (EA) Under of
the EA,
State
farms
the consent
is required
for
of the Secretary
the
construction,
in the UK
39
FEATURE
operation
or
station
extension
of more
capacity.
Further,
offence
above
50
under
to install
cable with
of any
than
ground,
except
from
anybody
wishing
shore
wind
farm
to the DTI
reference This
which
by the appropriate
Regulations
(EACR).
1990
The
EA also requires
be sent
to the relevant
and Wales,
authority.
However, powers
low water
mark
decision-making
of the planning
system.
farm
the mean
is not clear to which
the scope if a wind
authority
be made.
The
a situation
the local
it
required
the
to
development
in
all
therefore,
making
an application.
Under
these
must
desirability
of
fauna
special
also
the
and
interest,
buildings
objects
or archaeological
must
put procedures
gate damages
London
Gazette
newspaper. be
of
least,
also
served
the Secretary
of State’s powers
a notice
accompanying The
national
when
a
of publication,
objections
to the wind
should
also
and any
with the Secretary
of State.
may
is required
with
internal
waters
noted
of materials
the TWA,
consent
rights
under
rying
out
if a consent
procedure an
the
up to
obtaining
a
the carImpact
must
which
time
be lodged
If an objection
is
applicant
to discuss
difficulties.
preparation
of
an
Statement.
works
that, TWA
under gives
consent where
mandatory
hurdles
need
to
under
the EA.
applying
the EA, a separate permission
is
permission
under
sections
the
2001
required,
TCPA
RE’ ‘_
the
consents
that
seek
likelihood will
cost of all wind
advice
lifecycle the
from - not
procedures
apply
but
that,
if they
be granted
also
to are
in as
as possible.
of
References 1.
the
Copies
previous
the mandatory
able
either
at
article
deal-
issues are avail-
www.masons.com
www.re-focus.net/related/) 2.
Partner
3.
Partner
to
of Masons’
ing with
Should
* ’
In
of project
the ultimate
article
a timeframe
for planning
need
consideration.
whether
in this
or
means
under
required.
also
we believe should
of
occasion,
in the project
advise
are
a number
chances
to control
early
increase
short
into
developers
to
on
the
project,
described
36 or 37 of
application not
and
are
which,
increase
to the
developers
to be
TWA,
This
for an order
under
is usu-
in addition
there
be taken
to
only
it is
that,
to fulfil,
experts
control. where
the
be sent
Environment
the consent
procedures
required
farm
water
be deemed
under
the
Conclusion
any such
if the Secretary
order
or consent
November/December
planning
can
the TCPA
an
low
circumstances
permission
granted State
to TCPA
in those
mean
potential
two months.
So, it can be seen
order
above
any
will then
returned,
the who
the necessary
out
by
within
is
with
engineer,
prepare iron
form
Once
success
those
therefore, Agency
it is usual for the
The applicant
application
Agency.
and,
Agency
and
the
the Water
the proposals
Environment
other
Planning Permission Under the Town and Country Planning Act 1990 (TCPA). Only
199 1 (WRA)
In this instance,
local
with
of the Environment
ally processed
be
Environmental
and
watercourses,
required.
an
It should
for
Act
to erect a
in the
the TWA does require
of
is
that
and Wales,
waters.
may
a river, estuary
comply
will help the applicant
out and use
of navigation
smaller
must
documentation
a devel-
structures)
other
the consent
of
of a developer
in, over or under
Resources
on, under
to carry
of England
the
farm
development
such consent
whereby
utility
of territorial
that,
If it is the intention wind
for any
ot improvement
However,
(including
interfere
grants
Statement).
during
works
required,
to determine
published,
farm
under
However,
date of at least 28 days from the
last date
or depositing
level are subject
Nature
of the application
application,
the
it is within
Environmental
give a closing
EA
at the very
bodies
of State
Statement
Structures Erected in Watercourses or various
alteration
Environmental
for two
the
(Note,
interested
of the
a public
be held.
of the Secretary
Assessment
Interest,
on
Council.
be given
his-
the
one
must,
Conservancy other
sites,
the site in ques-
Scientific
of the application
be raised from
as to whether
an Environmental
or will
The Transport & Works Act 1992 (TWA) Asdetailed in our earlier article, the consent
the limits
of
newspaper,
at least should
notice
whether
the
be necessary.
finalised,
under
by the applicant,
Special
be
beauty,
Developers
When
in a local and
objections
oper can be authorised
of
of architectural, interest.
Further,
conditions
then it is at the discretion
should
obtained
the
features
application
weeks
obtained,
authority
the consent
does not need to be obtained
in place that will miti-
be published
successive
not
to
as protecting
in this regard.
of the
which
or over the seashore.
before
regard
geographical
toric
a notice
DTI
natural
as well
and
are
or supplier
have
preserving
Should
of State
inquiry
works,
and
Developers
the EA, a generator
electricity
tion
that
consult
be granted.
construction,
however,
Statements
instances.
should,
must
in the consul-
involvement,
noted
in
suggests planning along
This
be
it
runs
to Environmental
should
flora,
DTI
be involved
process.
is limited
mark
further
under
other sources
border the
or impose
Secretary
planning
the applica-
should
nearest
this
is outside low water
a relevant
of State must either hold a pub-
modifications
Therefore,
in such
tation
40
- beyond
from
the Secretary lic inquiry
the limit
that
should
received
the
is deemed
tion
question
within
to
is usually
authority’s
coastline
and Asia.
both
projects
for
authority
of a planning
whose
in the UK, Europe
of renewable
can
the application planning
local planning
authority
of offices
in a number
by
fee - a scale for which
is outside
involved
will be affected.
Consent)
limit,
law firm with a network
has been
group
also be accompanied
(Application
to be mean
is an international
energy
in
the land,
in the Electricity
in England
1
an off-
apply
be found
which,
WIND
of State.
to develop must
must
OFFSHORE
in accordance
and describe
to a map,
application
Masons The
an electric
the Secretary
Hence,
UK
Masons
the EA it is also an
or keep installed
a consent
writing
generating generating
MW
-
be
www.re-focmnet
group
- energy -
group
planning
&
environmental
or